Date Filed | Summary | Pages |
10/02/2013 | Case Status Form to close cases. | 1 |
09/23/2013 | Case Status form to close cases. | 1 |
10/16/2000 | ICN #0002 Entry ordering that the listed certificates of environmental compatibility and public need previously granted to OE, TE, and CEI for the construction and opera- tion of numerous electric transmission facilities (and associated transmission facilities) shall be transferred to ATSI; that, as a result of these transfers, ATSI shall be bound by and comply with all terms and conditions of these certificates. | 13 |
10/16/2000 |
ICN #0002 Entry ordering that the listed certificates of environmental compatibility and public need previously granted to OE, TE, and CEI for the construction and opera- tion of numerous electric transmission facilities (and associated transmission facilities) shall be transferred to ATSI; that, as a result of these transfers, ATSI shall be bound by and comply with all terms and conditions of these certificates
| 7 |
10/16/2000 | ICN #0055 Entry ordering that the listed certificates of environmental compatibility and public need previously granted to OE, TE, and CEI for the construction and opera- tion of numerous electric transmission facilities (and associated transmission facilities) shall be transferred to ATSI; that, as a result of these transfers, ATSI shall be bound by and comply with all terms and conditions of these certificates. (6 pgs.) | 6 |
12/16/1996 | Letter stating the completed date of project filed on behalf of applicant by G. L. Cunningham. (1 pg.) | 1 |
06/04/1996 | ICN #0053 Letter to Mr. T. C. Burgess stating that the engineering drawings submitted on May 13, 1996, have been reviewed by the staff and construction of the portion of the project depicted by the drawing may be started, filed on behalf of the PUCO staff by K. Wissman. (1 pg.) | 1 |
05/30/1996 | ICN #0052 Revised Sheet 6 of Plan and Profile drawing TZ-374-F of the Kirby-Tangy portion of the Crissinger- Tangy 138 kV project, filed on behalf of applicant by T. Burgess. (2 pgs.) | 2 |
05/30/1996 | ICN #0220 Revised Sheet 6 of Plan and Profile drawing TZ-374-F of the Kirby-Tangy portion of the Crissinger- Tangy 138 kV project, filed on behalf of applicant by T. Burgess. (2 pgs.) | 2 |
04/18/1996 | ICN #0051 Letter to Mr. T. C. Burgess, Ohio Edison, stating that they may proceed with construction of the portion of the project depicted by the drawing submitted on March 22, 1996, filed by K. Wissman, PUCO staff. (1 pg.) | 1 |
04/18/1996 | ICN #0050 Revised Sheet 8 of Plan & Profile drawing TZ-374-F of the Kirby-Tangy portion of the Crissinger- Tangy 138 kV project, filed on behalf of applicant by T. Burgess. (1 pg.) | 1 |
03/26/1996 | Final archaeological survey report filed on behalf of applicant by T. C. Burgess. (6 pgs.) | 6 |
01/26/1996 | ICN #0048 Letter to Mr. T. C. Burgess approving the drawings submitted on January 3, 1996, filed by K. Wissman, PUCO staff. (1 pg.) | 1 |
01/25/1996 | ICN #0047 Plan and profile drawings TZ-376-F, Sheets 1 & 2, filed on behalf of applicant by T. Burgess. (2 pgs.) | 2 |
01/04/1996 | Letter stating that the portion of the project depicted by the drawings may proceed with construction filed by K. Wissman, PUCO staff. (1 pg.) | 1 |
01/04/1996 | Revised sheets 3, Rev. C and 4, Rev. B of plan and profile drawing TZ-374-F of the Kirby-Tangy portion, and revised sheets 3, Rev. A;4, Rev. A; and 5, Rev. A of the Kirby- Roberts portion of the Crissinger-Tangy 138 kV project filed on behalf of applicant by T. C. Burgess. (7 pgs.) | 2 |
01/04/1996 | Highway crossing permit for S.R. 257 with the new expiration date filed on behalf of applicant by T. C. Burgess. (3 pgs) | 3 |
12/01/1995 | Letter stating drawing has been reviewed and construction may proceed filed by K. Wissman, PUCO staff. (1 pg.) | 1 |
11/30/1995 | Revised Kirby-Tangy Plan & Profile drawing TZ-374-f, sheet 8 filed on behalf of applicant by T. C. Burgess. (2 pgs.) | 2 |
11/08/1995 | ICN #0041 Copy of previously provided permit with the new expiration date, filed on behalf of applicant by T. Burgess. (2 pgs.) | 2 |
10/04/1995 | INC #0030 Revised Kirby-Tangy Plan & Profile drawings TZ- 374-F, Sheets 5A, 7B, 9A & 10A, filed on behalf of applicant by T. Burgess. (1 pg.) | 1 |
10/04/1995 | ICN #0040 Revised Kirby-Tangy Plan & Profile drawings TZ- 374-F, Sheets 5A, 7B, 9A & 10A, filed on behalf of applicant by T. Burgess. (1 pg.) | 1 |
10/04/1995 | ICN #0038 Revised Kirby-Tangy Plan & Profile drawings TZ- 374-F, Sheets 5A, 7B, 9A & 10A, filed on behalf of applicant by T. Burgess. (1 pg.) | 1 |
10/04/1995 | ICN #0029 Revised Kirby-Tangy Plan & Profile drawings TZ- 374-F, Sheets 5A, 7B, 9A & 10A, filed on behalf of applicant by T. Burgess. (1 pg.) | 1 |
10/04/1995 | ICN #0193 Revised Kirby-Tangy Plan & Profile drawings TZ- 374-F, Sheets 5A, 7B, 9A & 10A, filed on behalf of applicant by T. Burgess. (1 pg.) | 1 |
10/04/1995 | ICN #0029 Revised Kirby-Tangy Plan & Profile drawings TZ- 374-F, Sheets 6 & 7, filed on behalf of applicant by T. Burgess. (1 pg.) | 1 |
10/04/1995 | ICN #0039 Revised Kirby-Tangy Plan & Profile drawings TZ- 374-F, Sheets 6 & 7, filed on behalf of applicant by T. Burgess. (1 pg.) | 1 |
10/04/1995 | ICN #0037 Revised Kirby-Tangy Plan & Profile drawings TZ- 374-F, Sheete 6 & 7, filed on behalf of applicant by T. Burgess. (1 pg.) | 1 |
10/04/1995 | ICN #0028 Revised Kirby-Tangy Plan & Profile drawings TZ- 374-F, Sheete 6 & 7, filed on behalf of applicant by T. Burgess. (1 pg.) | 1 |
10/04/1995 | ICN #0192 Revised Kirby-Tangy Plan & Profile drawings TZ- 374-F, Sheets 6 & 7, filed on behalf of applicant by T. Burgess. (1 pg.) | 1 |
10/03/1995 | ICN #0028 Letter to Mr. T. C. Burgess stating that he may proceed with construction of those portions of the project depicted by the drawings submitted on September 11 and September 26, 1995, filed by K. Wissman, OPSB staff. (1 pg.) | 1 |
10/03/1995 | ICN #0038 Letter to Mr. T. C. Burgess stating the he may proceed with construction of those portions of the project depicted by the drawings submitted on September 11 and September 26, 1995, filed by K. Wissman, OPSB staff. (1 pg.) | 1 |
09/21/1995 | ICN #0037 Regional permit for the existing Scioto River crossing of DP&L's Delaware-Darby 138 kV transmission line, filed on behalf of applicant by T. Burgess. (6 pgs.) | 6 |
08/16/1995 | ICN #0036 Correspondence letter to T. C. Burgess, Ohio Edison, stating that they may proceed with the construction of those portions of the project depicted by the drawings, filed by K. Wissman, OPSB staff. (1 pg.) | 1 |
08/16/1995 | ICN #0035 Required highway crossing permits filed on behalf of appicant by T. Burgess. (2 pgs.) | 2 |
08/16/1995 | ICN #0034 Plan & profile drawings filed on behalf of applicant by T. Burgess. (3 pgs.) | 3 |
08/01/1995 | ICN #0033 Letter in response to the June 16, 1995 request for additional information, filed on behalf of applicant by T. Burgess. (9 pgs.) | 9 |
08/01/1995 | ICN #0032 Copy of the Department of the Army regional permit for crossing the Scioto River on the Kirby-Tangy 138 kV portion of the Crissinger-Tangy 138 kV transmission line project, filed on behalf of applicant by T. Burgess. (10 pgs.) | 10 |
06/20/1995 | ICN #0031 Correspondence letter to Mr. T. C. Burgess stat- ing that the engineering drawings for this project have been reviewed and construction of the project may begin, filed by K. Wissman, OPSB staff. (1 pg.) | 0 |
06/14/1995 | ICN #0030 Letter stating that the engineering drawings for this project have been reviewed by the staff and found to be consistent with the description of the facility certifiecated; therefore, applicant may proceed with construction of the portion of the project depicted by the drawings, filed by K. Wissman, OPSB staff. (1 pg.) | 0 |
06/13/1995 | ICN #0029 One set of three Plan and Profile drawings for the captioned 138 kV transmission line relocations at Tangy Substation, filed on behalf of applicant by T. Bur- gess. (2 pgs.) | 0 |
06/13/1995 | ICN #0028 OE's May 18, 1995 coordination letter with OHPO, and letter dated May 24, 1995 from OHPO concurring with survey results, filed on behalf of applicant by T. Burgess. (6 pgs.) | 0 |
06/13/1995 | ICN #0027 Copy of three of the Union County permits for work within road rights-of-way of Township 355, County Road 265 (Hoskins Road), and County Road 264; and copy of blanket permit 95-22 covering work within road rights-of- way of Union County, filed on behalf of applicant by T. Burgess. (6 pgs.) | 0 |
05/17/1995 | ICN #0026 Route and property drawings filed on behalf of applicant by T. Burgess. (29 pgs.) | 0 |
05/17/1995 | ICN #0025 Management Summary which provides a description of the survey associated with this project, filed on behalf of applicant by T. Burgess. (6 pgs.) | 0 |
05/17/1995 | ICN #0024 Required highway crossing permits for three locations on the Kirby-Tangy 138 kV portion of the Crissinger_Tangy lineproject, filed on behalf of applicant by T. Burgess. (6 pgs.) | 0 |
05/17/1995 | ICN #0023 OE's April 20, 1995 coordination letter with OHPO, and letter dated May 3, 1995 from OHPO concurring with the survey, filed on behalf of applicant by T. Burgess. (4 pgs.) | 0 |
05/17/1995 | ICN #0022 Letter clarifying the correct designation (33-DL- 868) of the potentially significant site, filed on behalf of applicant by T. Burgess. (2 pgs.) | 0 |
04/14/1995 | ICN# 0021 Concurrence letter from the ODNR and USF&WS. Also aerial drawings and January 19, 1995 letter to the ODNR and USF&WS describing the potential bat habitat areas filed on behalf of Ohio Edison Company by T. V. Burgess. (5 pgs) | 0 |
04/14/1995 | INC# 0020 Materials describing the results of the archaeo- logy field survey and OHPO review of the first segment, including the management summary, filed on behalf of Ohio Edison by T. C. Burgess. (19 pgs) | 0 |
03/16/1995 | ICN #0019 Route and property drawings as listed on Exhibit OE-1, filed on behalf of applicant by T. Burgess. (3 pgs.) | 0 |
03/15/1995 | ICN #0018 Letter stating that the route and property draw- ings for the Crissinger-Tangy project, submitted on 2/21/95, have been reviewed by the staff, and Ohio Edison may pro- ceed with construction of the portion of the project depicted by the drawings, filed by K. Wissman, OPSB staff. (1 pg.) | 0 |
02/03/1995 | ICN #0017 Additinal information filed on behalf of applicant by T. Burgess. (12 pgs.) | 0 |
12/19/1994 | ICN # 0016 Opinion & Order approving the stipulation in its entirety; that Ohio Edison investigate the matter raised by Mr. Hooper and report back to staff within 45 days; that the Certificate issued to Ohio Edison on 9/20/93 is hereby amended to reflect the amended line routes set forth in the amendment application. (OSB) (7pgs.) | 0 |
12/08/1994 | ICN #0015 Correspondence letter regarding the application, filed by A. Hooper. (4 pgs.) | 0 |
12/05/1994 | ICN #0014 Transcript filed for hearing held 11/15/94, (DB), 35 pgs., Submitted. | 0 |
12/05/1994 | ICN #0013 Transcript filed for hearing held 11/14/94, (DB), 11 pgs., Con't. (Richwood, Ohio) | 0 |
11/15/1994 | ICN #0012 Joint stipulation regarding application to amend certificate filed on behalf of applicant by M. Beiting and the OPSB staff by D. Luckey. (9 pgs.) | 0 |
11/09/1994 | ICN #0011 Notice of appearance filed on behalf of the OPSB staff by D. Luckey and E. Leidner. (2 pgs.) | 0 |
10/28/1994 | Staff Report Filed. | 25 |
10/28/1994 | ICN #0010 Proofs of publication filed on behalf of applicant by T. Burtess. (6 pgs.) (Delaware, Union, Marion Counties) | 0 |
10/27/1994 | ICN #0008 Response to OPSB staff's requests for production of documents and interrogatories, first set, filed on behalf of applicant by M. Beiting. (18 pgs.) | 0 |
10/07/1994 | ICN #0007 Combined requests for producion of documents and interrogatories, first set, filed on behalf of the OPSB staff by D. Luckey. (12 pgs.) | 0 |
09/30/1994 | ICN #0006 Entry scheduling a local public hearing at 7:00 p.m. on 11/14/94 at the cafeteria of the North Union High School, Richwood, Ohio; scheduling an adjudi- catory hearing at 10:00 a.m. on 11/15/94 at the Commission offices. (AE) (3 pgs.) | 0 |
09/28/1994 | ICN #0005 Notification of service letter, affidavit of service, and service list filed on behalf of applicant by M. Beiting. (6 pgs.) | 0 |
08/31/1994 | ICN #0004 Letter to Mr. B. M. Miller stating that the application has today been certified as being complete, filed by the OPSB staff. (2 pgs.) | 0 |
08/29/1994 | ICN# 0003 Proof of service of amendment to the certificate for Crissinger-Tangy 138 kV Transmission Line Project filed on behalf of Ohio Edison Company by T.C. Burgess. | 2 |
08/29/1994 | ICN #0003 Affidavit of service of Donald P. Morrison, Jr. filed on behalf of applicant by T. Burgess. (2 pgs.) | 0 |
07/20/1994 | ICN #0002 Entry ordering that all further filings made regarding the Crissinger Substation, Tawa Road, Brindle Road, and Smart Road amendments be filed under the appropriate case docket identified in Finding No. 3. (OPSB) | 0 |
07/20/1994 | Entry ordering that all further filings made regarding the Crissinger Substation, Tawa Road, Brindle Road, and Smart Road amendments be filed under the appropriate case docket identified in Finding 3. (SF) | 2 |
07/15/1994 | ICN #0001 In the matter of application for amendment to the certificate of environmental compatibility and public need for the Crissinger-Tangy 138 kV Transmission Line Project, Smart Road Area Realignment, Delaware County. | 0 |