Date Filed | Summary | Pages |
12/10/2001 | Proof of check receipt filed. | 1 |
07/17/2000 | Entry dismissing this case and closing it of record; that any application fees associated with Case Number 93-984-GA-BTX that may not have been spent should be returned to COH. (OPSB) | 5 |
05/26/2000 | ICN #0025 Motion seeking withdrawal of its application and memorandum in support filed on behalf of applicant by D. Keenan. (4 pgs.) | 4 |
11/27/1995 | ICN #0024 Additional information filed on behalf of applicant by A. Koncelik. (16 pgs.) | 16 |
09/01/1995 | Letter stating the application has been found incomplete filed on behalf of the PUCO staff. (1 pg.) | 1 |
08/29/1995 | Correspondence letter stating no objections to the Roachton road alignment filed on behalf of the City of Perrysburg by J. Bagdonas. (1 pg.) | 1 |
07/05/1995 | ICN #0021 Amended application filed on behalf of applicant by K. Christman. (277 pgs.) | 0 |
07/05/1995 | ICN #0020 Motion for a waiver of O.A.C. Rule 4906-5-03(B) and memorandum in support filed on behalf of applicant by K. Christman. (4 pgs.) | 0 |
03/01/1994 | ICN #0019 Entry ordering that the motion of Columbia Gas of Ohio, Inc. for a suspension of the hearing schedule in this case be granted and further hearings in this matter be delayed until after Columbia has filed an amended certificate application. (OPSB) | 0 |
02/28/1994 | ICN #0018 Transcript filed for hearing held 2/16/94, (SD), 21 pgs., Con't. (Perrysburg, Ohio) | 0 |
02/24/1994 | ICN #0016 Transcript filed for hearing held 2/18/94, (SD), 5 pgs., Con't. | 0 |
02/24/1994 | ICN #0017 Motion to suspend hearing schedule and memorandum in support filed on behalf of applicant by K. Christman. | 0 |
02/15/1994 | ICN#0015 Proof of publication filed on behalf of the applicant by K. Christman. | 0 |
02/08/1994 | ICN #0014 Motion for continuance of adjudicatory hearing and memorandum in support filed on behalf of applicant by K. Christman. | 0 |
02/01/1994 | ICN #0013 Staff report filed. | 0 |
12/10/1993 | ICN #0012 Responses of Columbia Gas of Ohio, Inc. to the November 15, 1993 interrogatories and requests for the production of documents, filed by K. Christman. | 0 |
12/02/1993 | ICN #0011 Entry ordering that the local public hearing be continued to 2/16/94 at 7:00 p.m. at the Perrysburg Municipal Bldg., Perrysburg, Ohio; that the adjudicatory hearing be continued to 2/18/94 at 10:00 a.m. at the Commission offices. (OPSB) | 0 |
11/29/1993 | ICN #0010 Motion for a continuance and request for an expedited ruling submitted on behalf of the staff of the Power Siting Board by A. Hammerstein. | 0 |
11/18/1993 | ICN #0009 Entry scheduling a hearing at 7:00 p.m. on 1/11/94 at the Perrysburg Municipal Building, Perrysburg, Ohio; scheduling an adjudicatory hearing at 10:00 a.m. on 1/13/94 at the Commission offices. (OPSB) | 0 |
11/15/1993 | ICN #0008 Combined requests for production of documents and interrogatories filed on behalf of the OPSB staff by A. Hammerstein and G. Kelly. | 0 |
10/29/1993 | ICN #0007 Certified application filed on behalf of applicant by K. Christman. | 0 |
10/27/1993 | ICN#0006 Notice to intervene filed on behalf of the City of Perrysburg filed by J. Bagdonas. | 0 |
10/15/1993 | ICN #0005 Notice of appearance filed on behalf of the PUCO staff by A. Hammerstein and G. Kelly. | 0 |
09/27/1993 | ICN #0004 Letter to Anthony W. Amurgis, Columbia Gas, stating that the application has been certified as being complete in accordance with Ohio Administrative Code Rule 4906-1-14 (A)(1), submitted by C. Glazer, OPSB staff. | 0 |
08/31/1993 | ICN #0003 Supplement to the application, filed on behalf of applicant by K. Christman. | 0 |
08/10/1993 | ICN #0002 Letter stating that Columbia Gas will submit the additional information to supplement its application by September 1, 1993, filed by K. Christman. | 0 |
06/14/1993 | ICN #0001 In the matter of the application of Columbia Gas of Ohio, Inc. for a certificate of environmental compatibility and public need, authorizing construction of the Toledo 20-Inch Southern Loop. | 0 |