03/15/1994 | Letter stating that on March 10, 1994 Masury Water Company completed the special mailing of its customers notice of the rate increase, filed by J. Sanders. | 0 |
03/11/1994 | Revised tariff sheets filed on behalf of applicant by J. Sanders. | 0 |
03/10/1994 | Opinion and Order granting the application. | 0 |
02/22/1994 | Stipulation and recommendation filed on behalf of applicant by J. Sanders and the PUCO staff by W. Wright. | 0 |
01/10/1994 | Proof of Publication filed by J. Sanders. | 0 |
12/13/1993 | Transcript filed for hearing held 11/22/93, (WB), 19 pgs., Con't. (Brookfield, Ohio) | 0 |
12/01/1993 | Transcript filed for hearing held 11/16/93, (WB), 6 pgs., Con't. | 0 |
11/03/1993 | Proofs of publication filed on behalf of applicant by J. Sanders. (Trumbull and Mercer Counties) | 0 |
10/29/1993 | Entry scheduling a local public hearing at 5:00 p.m. on 11/22/93 at the Brookfield Township Administration Building, Brookfield, Ohio; that notice of the hearing be published as directed in Finding 2. (AE) | 0 |
10/26/1993 | Entry ordering that the motion to extend the time to file supplemental testimony is granted. (AE) | 0 |
10/22/1993 | Objections to the staff report filed on behalf of applicant by J. Sanders. | 0 |
10/22/1993 | Summary of major issues filed on behalf of applicant by J. Sanders. | 0 |
10/21/1993 | Motion for extension of time to file testimony and memor- andum in support filed on behalf of applicant by J. Sanders. | 0 |
10/13/1993 | Entry ordering that all motions to strike objections must be filed by 11/5/93; memorandum contra such motions by 11/12/93; scheduling a prehearing conference at 10:00 a.m. on 11/9/93 at the Commission offices; scheduling a public hearing at 9:00 a.m. on 11/16/93 at the Commission offices. (AE) | 0 |
09/23/1993 | Staff report filed | 0 |
04/29/1993 | Entry accepting rate application for filing as of March 10, 1993; that the proposed newspaper notice submitted by Masury Water Company is approved, as amended, for publi- cation as set forth in Finding 6. | 0 |
04/09/1993 | Schedules E-3 and E-3.1 which should be added to the E Schedule Section of the application, and correction to schedules previously filed, filed on behalf of applicant by J. Sanders. | 0 |
03/31/1993 | Direct testimony of Robert G. Liptak filed on behalf of applicant by J. Sanders. | 0 |
03/31/1993 | Direct testimony of Robert A. Kopas filed on behalf of applicant by J. Sanders. | 0 |
03/31/1993 | Direct testimony of Kenneth W. Reeves filed on behalf of applicant by J. Sanders. | 0 |
03/31/1993 | Direct testimony of John Van C. Parker filed on behalf of applicant by J. Sanders. | 0 |
03/11/1993 | Entry ordering that the test period of the applicant shall begin October 1, 1992 and end September 30, 1993, and the date certain shall be December 31, 1992. | 0 |
03/10/1993 | Application filed on behalf of applicant by J. Sanders. | 0 |
02/03/1993 | In the matter of the notice of intent of Masury Water Company for authority to increase its rates and charges. | 0 |