10/14/1993
|
Entry ordering that Conrail proceed with the installation of the corridor project in Mt. Victory, Ohio, to be com- pleted by 10/14/94. |
10/13/1993
|
Copy of the construction authority received from the Federal Highway Administration filed by B. Johrendt. |
07/16/1993
|
Memo stating that the Railroad Section has received the total package of the plans and estimates for the Conrail/ Closure Project, and cover letters filed by J. D. Cossel, Chief Engineer, Design and Construction, Conrail, dated July 13, 1993, filed by B. Johrendt, PUCO staff. |
04/15/1993
|
Entry adopting the stipulation and recommendation and ordering that the Commission pay its share of the project cost as set forth herein; that Conrail submit for Commission approval site plans and cost estimates for the installation project within 90 days of the date of this entry. |
04/01/1993
|
Stipulation and recommendation filed on behalf of the Village of Mt. Victory by N. Jolliff; Consolidated Rail Corp. by G. M. Williams; ODOT by J. Wray; and the PUCO staff by A. Agler. |
12/21/1992
|
In the matter of the request regarding a Corridor Project, with the installation of active warning devices with road- way gates, rail-high surfaces, and grade crossing closures to vehicles at various locations in the City of Mt. Victory, Hardin County, Conrail. |
|