DIS - Case Record for 92-2214-EL-BLN Skip to main content
      
      
CASE NUMBER: 92-2214-EL-BLN
CASE DESCRIPTION: DAYTON POWER & LIGHT/CLARKSBURG
DOCUMENT SIGNED ON: 5/6/2024
DATE OF SERVICE: ________________________________________
09/30/1993 ICN #0006 Letter notifying the OPSB that the construction on this project was completed on September 17, 1993, and residual sitework and cleanup will continue for approxim- ately two weeks, filed on behalf of applicant by D. Winkel- john.
09/22/1993 ICN #0005 Letter informing the Commission that the Clarks- burg Substation is scheduled to be energized as of September 17, 1993, filed on behalf of applicant by H. Shamash.
09/09/1993 ICN #0004 Notification to the Ohio Power Siting Board that the referenced project is scheduled to begin construction project approximately 9/10/93, and should be concluded 9/19/93, filed on behalf of applicant by D. Winkeljohn.
03/16/1993 ICN #0003 Letter providing notice of the planned commence- ment of construction on March 20, 1993, filed on behalf of applicant by H. Shamash.
01/14/1993 ICN #0002 Response to Mr. Thomas M. Jenkins to letter of notification, filed by K. Wissman, PUCO staff.
12/04/1992 ICN #0001 In the matter of the Letter of Notification of The Dayton Power & Light Company to build a 345/69 KV distribution substation in Pickaway County, Ohio.