04/27/1993
|
ICN #0005 Letter informing the Commission that construction on this project was completed on April 18, 1993, filed on behalf of applicant by J. Ams. |
12/31/1992
|
ICN #0004 Letter stating that the planned date of initial construction on this project is the week of January 4, 1993, filed on behalf of applicant by M. Ams. |
12/18/1992
|
ICN #0003 Letter to Mr. Gary J. Greben in response to letter of notification, filed on behalf of the OPSB staff by K. Wissman. |
12/18/1992
|
ICN #0002 Investigation report Letter of Notification filed on behalf of the OPSB staff. |
11/20/1992
|
INC #0001 In the matter of the Letter of Notification of Cleveland Electric Illuminating Co. pursuant to OAC 4906- 1-01 and Appendix A covering the installation of a 138kv transmission line to serve the Painesville Electric System substation. |