Date Filed | Summary | Pages |
10/22/1992 | Entry dismissing complaint since the conditions giving rise to the complaint have been corrected. | 0 |
10/07/1992 | Report submitted by Inspector J. L. White, filed on behalf of the PUCO staff by G. Sandridge. | 0 |
09/10/1992 | Report and memo stating that this matter be held in abey- ance pending completion of the work as indicated and a final inspection, filed on behalf of the PUCO staff by G. Sandridge. | 0 |
08/20/1992 | Complaint letter and copy of complaint mailed to: John Dulac, Wheeling & Lake Erie Railway Co. | 0 |
08/20/1992 | Complaint letter and copy of complaint mailed to: Steven W. Wait, Wheeling & Lake Erie Railway Co. | 0 |
08/20/1992 | Complaint letter and copy of complaint mailed to: Larry Parson, Wheeling & Lake Erie Railway Co. | 0 |
08/19/1992 | In the matter of the complaint of the Co-Operative Legis- lative Committee, United Transportation Union, (vs) the Wheeling & Lake Erie Railway Company relative to the alleged excessive vegetation, MP 93, from derail to a point about 300 feet beyond, Ashland Railroad Transfer Tract, ACY District. | 0 |