10/08/1993
|
Memo closing case with effective date of 10/8/93. |
08/11/1992
|
ICN #0004 Letter stating that construction is scheduled to begin on July 27, 1992, filed on behalf of applicant by T. Burgess. |
06/03/1992
|
ICN #0003 Response to Letter of Notification, filed on behalf of the OPSB staff by J. Kennedy. |
06/03/1992
|
ICN #0002 Investigation report filed on behalf of the OPSB staff by R. Yerian. |
05/07/1992
|
ICN #0001 In the matter of the Letter of Notification for the rebuilding of a portion of the South Akron-West Canton 138 kV transmission line by reconductoring 4.85 miles of 200 kcmil cu conductors with 605 kcmil ACSR conductors, submitted by Ohio Edison Company. |