10/08/1993 | Memo closing case with effective date of 10/8/93. | 0 |
05/28/1992 | ICN #0005 Letter stating that the construction was completed on May 15, 1992, filed on behalf of applicant by T. Burgess. | 0 |
05/12/1992 | ICN #0004 Letter stating that construction of this project is to begin on April 6, 1992, filed on behalf of applicant by T. Burgess. | 0 |
11/26/1991 | ICN #0003 Letter in response to Letter of Notification filed on behalf of the OPSB staff by J. Kennedy. | 0 |
11/26/1991 | ICN #0002 Investigation Report Letter of Notification filed on behalf of the OPSB staff. | 0 |
11/05/1991 | ICN #0001 Letter of Notification describing the replacement of four wood pole structures on the centerline of the existing Johnson-U. S. Steel 138 kV transmission line. | 0 |