12/09/1993 ICN #0006 Letter informing the Commission that the constru- tion on this project was completed on 11/29/93, filed on behalf of applicant by T. Denzler.
10/08/1993 Memo closing case with effective date of 10/8/93.
07/07/1993 ICN #0005 Archaeological report, "Phase III Evaluative Testing for the Horizon Substation Project Area (Part Two)", filed on behalf of applicant by M. Ams.
02/11/1992 ICN #0004 Letter requesting that the OPSB staff recommend that all requirements for the Horizon Supply Letter of Notification are now met, and that the OPSB board approve this project, filed on behalf of applicant by M. Ams.
02/06/1992 ICN #0003 Letter stating that the informational requirements for a Letter of Notification have been met and the project may proceed, privided that the agreements outlined in the letter of 2/3/92 to the Ohio Power Siting Board are adhered to, filed on behalf of the PUCO staff by J. Kennedy.
01/28/1992 ICN #0002 Letter acknowledging the extended time needed for OPSB review of the Horizon Supply LON and stating that con- struction has been deferred from June 1992 to September 1992, filed on behalf of applicant by M. Ams.
08/30/1991 ICN #0001 In the matter of the Letter of Notification filed by Centerior Service Company on behalf of Cleveland Electric Illuminating Company for the Horizon Supply Line.