04/14/1994
|
Entry ordering that this case be removed from the Commission's docket and closed of record. |
10/10/1991
|
Entry ordering the period of performance and the contract amount between CG&E, DP&L and CSP with Endispute, Inc. be changed from February 6, 1991 to October 31, 1991; and that associated costs be increased by $20,000; the Commission directs the total costs be paid by CG&E, DP&L and CSP to Endispute, Inc. in an amount not to exceed $194.628. |
08/22/1991
|
Entry changing the period of performance of the contract agreement between CG&E, DP&L, and CSP with Endispute, Inc. to 2/6/91 through 9/30/91. |
04/26/1991
|
Motion to intervene and memorandum in support filed on behalf of the Miami Township Board of Trustees and Clay Township Board of Trustees by J. Migden. |
01/17/1991
|
Entry ordering the companies to make appropriate contract arrangements with Endispute, Inc. |
01/08/1991
|
In the matter of the alternative resolution dispute in regard to Zimmer Power Plant. |
|