Date Filed | Summary | Pages |
01/04/1996 | Entry closing case. (2 pgs.) | 2 |
12/20/1995 | Final inspection reports submitted on behalf of the PUCO staff by B. Johrendt. (4 pgs.) | 4 |
01/09/1995 | Supplemental inspection report of Inspector Gary A. Sand- ridge filed by B. Johrendt, PUCO staff. (3 pgs.) | 0 |
01/03/1995 | Final inspection report by Inspector Gary A. Sandridge, filed on behalf of the PUCO staff by B. Johrendt. (4 pgs.) | 0 |
12/15/1994 | Entry ordering that CSX shall complete installation of the Thrid Street, City of Willard, Huron County crossing by 2/14/95. (3 pgs.) | 0 |
12/08/1994 | Petition for short extension of time to install warning devices at Willard, Ohio, filed on behalf of CSX Trans- portation by W. Poynter. (7 pgs.) | 0 |
03/16/1994 | Entry approving the site plans and estimates submitted by CSX; that CSX complete the closure and installation pro- jects as quickly as possible, but not later than nine months from the issuance of this entry. | 0 |
03/07/1994 | Findings filed on behalf of the PUCO staff by B. Johrendt. | 0 |
02/04/1994 | Memo stating that the Railroad Section has received site plans and estimates for the Main Street and East Ave., City of Deshler, Henry County, crossing, with attached correspondence from J. W. Wollenzien, CSX Transportation, filed by B. Johrendt, PUCO staff. | 0 |
11/08/1993 | Letter correcting the request for an extension of time in which to submit design plans and specifications and stating the requested filing date of February 8, 1994 instead of December 8, 1993, filed on behalf of CSX Transportation by W. Poynter. | 0 |
11/03/1993 | Entry ordering that the petition for an extension of time to submit the site plans and cost estimates for this project is granted and CSX Transportation shall submit for Commission approval site plans and cost estimates by 2/8/93. | 0 |
10/15/1993 | Petition for extension of time to file design plans and specifications filed on behalf of applicant by W. Poynter. | 0 |
08/12/1993 | Entry adopting the stipulation and recommendation; that the Commission pay the public share of the costs of the projects; that CSX Transportation submit for Commission approval site plans and cost estimates for the installation projects within 90 days of the date of this entry; that CSX proceed with the installation of light signals and roadway gates at the Holmes Road, highway/railroad gradw crossing, to be completed no later than March 20, 1994. | 0 |
06/21/1993 | Stipulation and recommendation filed on behalf of PUCO staff by A. Agler, CSX Transportation by P. Van Cleve, the Village of Deshler by D. Morrison, the City of Tiffin by D. Martian, Ripley Township by D. Ray, the City of Willard by C. Morris, the Village of Creston by D. McGuire, and the Village of Lowellville by J. Olson. | 0 |
06/07/1993 | Corrections to the stipulation and recommendation regarding the McGill St. crossing, filed on behalf of the Village of Lowellville by J. Olson. | 0 |
07/17/1991 | Resolution No. 91-29 filed on behalf of the Village of Deshler by K. Diem and submitted to Docketing by G. Sandridge, PUCO staff. | 0 |
06/03/1991 | Correspondent letter filed on behalf of the John H. Hanna, Prosecuting Attorney, Henry County. | 0 |
01/31/1991 | Entry ordering the Railroad Dept. investigate and submit a written report of its findings. | 0 |