DIS - Case Record for 90-1423-RR-UNC Skip to main content
      
      
CASE NUMBER: 90-1423-RR-UNC
CASE DESCRIPTION: PUCO/CONSOLIDATED RAIL CORPORATION
DOCUMENT SIGNED ON: 7/17/2024
DATE OF SERVICE: ________________________________________
11/05/1992 Entry closing case.
10/13/1992 Final inspection report submitted by Inspector W. J. Johnson, filed on behalf of the PUCO staff by B. Johrendt.
09/17/1992 Interoffice memorandum, with attached status report from F. K. Giamoca, Conrail, stating that the warning devices are expedted to be activated by September 30, 1992, filed on behalf of the PUCO staff by B. Johrendt.
08/18/1992 Status report filed on behalf of the PUCO staff by B. Johrendt.
06/18/1992 Entry granting Consolidated Rail an extension of time until 8/14/92 to complete the installation of crossing protections.
06/01/1992 Memorandum stating that the PUCO staff has no objection to the requested extension of time until August 14, 1992, filed by R. Patterson.
06/01/1992 Letter requesting an extension of the deadline to August 29, 1992 to finish project, filed on behalf of Consolidated Rail Corp. by J. Cossel.
04/03/1992 Final inspection report filed on behalf of the PUCO staff by R. Patterson.
03/12/1992 Entry giving Consolidated Rail an extension of time until 5/29/92 in which to complete the installation of the highway/railroad grade crossing protection.
03/10/1992 Final inspection report submitted on behalf of the PUCO staff by R. Patterson.
02/18/1992 Memo from R. Patterson, PUCO staff, with attached request to extend the deadline for the construction of warning devices, submitted on behalf of respondent, Conrail, by J. Cossel.
10/10/1991 Findings and statement that Conrail has conplied with the Entry relating to the crossings in report, filed on behalf of PUCO staff by R. Patterson.
06/27/1991 Entry authorizing Consolidated Rail Corp. and CSX Trans- portation, Inc. to proceed with the installation of crossing protections to be completed by 3/7/92.
06/19/1991 Cover letter to Mr. Rand Patterson, PUCO staff, from Mr. J. D. Cossel, Consolidated Rail Corp., with attached plans and estimates for this project, filed on behalf of the PUCO staff by R. Patterson.
06/04/1991 Plans and estimates filed on behalf of Consolidate Rail by J. Cossel.
06/04/1991 Plans and estimates for the subject case filed on behalf of the applicant by J. Cossel.
06/04/1991 Plans and estimates filed on behalf of Consolidated Rail by J. Cossel.
06/04/1991 Plans and estimates filed on behalf of CSX Transportation Corp. by J. G. Eicher.
03/07/1991 Entry ordering that the Stipulations and Recommendations be adopted by the Commission; that the Commission pay the public share of the project costs designated as "PUCO share"; that Consolidated Rail Corporation and CSX Transportation submit for Commission approval site plans for the installation projects within 90 days of the date of this entry.
01/14/1991 Stipulation and Recommendation filed on behalf of Conrail by D. A. Swanson and the PUCO staff by R. Patterson.
12/14/1990 Stipulation and recommendation filed on behalf of the PUCO staff by R. Patterson.
09/12/1990 In the matter of the joint request of Consolidated Rail Corporation and the Staff of the Public Utilities Commission of Ohio regarding the installation of active warning devices of certain grade crossing locations on State Highway Routes.