10/08/1993
|
Memo closing case with effective date of 10/8/93. |
09/14/1990
|
ICN #0006 Letter stating that construction is scheduled to begin on August 27, l990, filed on behalf of applicant by T. Burgess. |
09/11/1990
|
ICN #0005 Letter stating that the date of completion of construction was August 3l, l990, filed on behalf of applicant by T. Burgess. |
08/06/1990
|
ICN# 0004 Letter filed by J. Kennedy stating that the application qualify's for a Letter of Notification and that the invoice for the direct cost is forthcoming. |
08/06/1990
|
ICN# 0003 Site visit letter stating that the application qualify's as a Letter of Notification filed by M. Apanius. |
07/31/1990
|
ICN #0002 Letter of Notification of Niles-Bluebell l38 kV, Bluebell-Highland l38 kV Structure Replacement and Relocation filed on behalf of Ohio Edison Company by C. Fleming. |
07/31/1990
|
ICN #0001 Request for Waiver of ninety day filing requirement prior to construction of Niles-Bluebell l38 kV, Bluebell-Highland l38 kV Structure Replacement and Relocation filed on behalf of Ohio Edison Company. |