DIS - Case Record for 90-0875-EL-BLN Skip to main content
      
      
CASE NUMBER: 90-0875-EL-BLN
CASE DESCRIPTION: OHIO EDISON COMPANY
DOCUMENT SIGNED ON: 4/18/2024
DATE OF SERVICE: ________________________________________
10/08/1993 Memo closing case with effective date of 10/8/93.
12/23/1991 ICN #0005 Letter stating that the construction completion date was September 19, 1991, filed on behalf of applicant by T. Burgess.
08/06/1991 ICN #0004 Letter stating that construction is scheduled to begin on July 15, 1991, filed on behalf of applicant by T. Burgess.
06/01/1990 ICN# 0003 Letter sent to B.M. Miller stating that the application qualifies for a letter of notification and that an invoice will be forthcoming filed by J. Kennedy.
06/01/1990 ICN# 0002 Site visit letter filed by J. Kennedy stating that the application qualify for a letter of notification.
05/21/1990 ICN #0001 Letter of Notification to construct 0.64 miles of new double circuit l38 kV transmission line from the Evergreen-Highland #3 l38 kV transmission line into the Burton Substation filed by Ohio Edison Company.