12/06/1990
|
Memo from R. Gooden, PUCO staff, stating that this case is closed. |
07/10/1989
|
ICN. #0006 Letter filed by J. E. Schrader on behalf of Ohio Power Company, informing the OPSB that construction has been completed. |
02/28/1989
|
ICN# 0005 Letter filed on behalf of the applicant stating that construction will begin on March 1, 1989 filed by J. Heppner. |
02/02/1989
|
ICN. #0004 Memo from L. Winget, OPSB, RE: Letter of Notification for the relocation of a 138kV transmission to by-pass an area which is being surface mined for coal. |
02/02/1989
|
ICN. #0003 Memo from J. Kennedy on behalf of OPSB, to; T. Chema, RE: to the Letter of Notification for the relocation of 138kV transmission. |
02/02/1989
|
ICN. #0002 Letter filed by J. Kennedy on behalf of the OPSB, RE: to the cost of processing the Letter of Notifi- cation and requesting the company to notify the Board at least 7 days prior to the planned date of initial construc- tion and of the completion date of the project within 7 days. |
12/28/1988
|
ICN. #0001 Letter of Notification for a proposed 1.99 mile relocation of the Newcomerstown - South Coshocton 138 KV Line by Ohio Power Company. |