Date Filed | Summary | Pages |
11/24/1987 | Opinion & Order closing case. | 0 |
10/07/1987 | Trans., for hearing held on 10/6/87, (SF) Submitted Vol. I, 1-11 pages. | 0 |
10/06/1987 | Joint Stipulation by all parties in settlement of issues, T. McNamee, PUCO staff, E. Rizer, DP&L Co. and J. Pepper, OCC. | 0 |
09/22/1987 | Direct Testimony of John A. Bucklew filed on behalf of DP&L Co. | 0 |
09/22/1987 | Direct Testimony of Teresa F. Marrinan filed on behalf of DP&L Co. | 0 |
09/04/1987 | Management/Performance Audit by Touche Ross on behalf of applicant. | 0 |
09/03/1987 | Facts, Data or other information relating to the company's gas cost recovery rates Section 4901:1-14-08-(C) Ohio Administrative Code, filed by J. Jensen on behalf of applicant. | 0 |
09/01/1987 | Gas Cost Recovery Mechanism for the effective three-month periods ending 2/28, 5/31, 8/31, and 11/30/87 filed on behalf of applicant submitted by Price Waterhouse. | 0 |
08/18/1987 | Entry ordering DP&L to revise its contract with auditor. | 0 |
06/01/1987 | Letter advising DP&L has selected Price Waterhouse to preform audits in cases 87-27-GA-GCR and 87-107-EL-EFC filed by P. Anderson. | 0 |
04/28/1987 | Entry ordering that Management/Performance Audits of the Gas Purchasing Practices and Policies of Regulated Gas Distribution Companies be conducted in accordance with provisions of RFP No. GCR 87 pursuant to Findings of this Entry. | 0 |
03/31/1987 | Entry granting OCC intervention. (AE) | 0 |
03/19/1987 | Motion to Intervene filed by J. Pepper on behalf of OCC. | 0 |
03/03/1987 | Entry scheduling case for hearing on September 4, 1987, at 10:00 a.m., at the offices of the Commission. | 0 |
01/06/1987 | In the matter of the regulation of the purchased gas adjust- ment clause contained within the rate schedule of the Dayton Power and Light Company and related matters. | 0 |