Date Filed | Summary | Pages |
08/11/1987 | Opinion & Order closing case. | 0 |
07/31/1987 | Trans., for hearing held on 7/28/87, (LR) Submitted Vol. I 1-9 pages. | 0 |
06/26/1987 | Audit of the gas cost recovery mechanism for the effictive GCR period May 1,1985 to October 31, 1986 filed on behalf of the Pike Natural Gas Company. | 0 |
04/28/1987 | Entry granting Pike exemption from the management/per- formance portion of the audit. | 0 |
04/13/1987 | Motion for Exemption filed on behalf of Pike Natural Gas Company by R. Taylor. | 0 |
03/03/1987 | Entry scheduling case for hearing on June 26, 1987, at 10:00 a.m., at the offices of the Commission. | 0 |
01/06/1987 | In the matter of the regulation of the purchased gas adjust- ment clause contained within the rate schedule of the Pike Natural Gas Company and related matters. | 0 |