09/09/1987
|
Opinion & Order closing case. |
08/26/1987
|
Trans., for hearing held on 8/11/87, (SF) Submitted Vol. I, 1-7 pages. |
06/30/1987
|
Proof of Publication filed/Columbiana |
06/18/1987
|
Trans., for hearing held on 6/9/87, (SF) Con't. Vol. I, 1-7 pages. |
05/08/1987
|
Audit of the gas cost recover mechanism for the effective GCR period June 1, 1985 to February 28, 1986, submitted by M. Kotting, Wm. Purdin, Jr. and J. Cowin on behalf of the PUCO staff. |
03/03/1987
|
Entry scheduling hearing on Tuesday 6/9/87, at 10:00 a.m., at the offices of the Commission. |
01/06/1987
|
In the matter of the regulation of the purchased gas adjust- ment clause contained within the rate schedule of the Murphy Gas, Inc. and related matters. |
|