CASE NUMBER: 24-0433-EL-BNR
CASE DESCRIPTION: South Coshocton – Wooster 138 kV Transmission Line Rebuild Project Phase 1
DOCUMENT SIGNED ON: 9/18/2024
DATE OF SERVICE: ________________________________________
07/23/2024 Service Notice.
07/22/2024 Response to Staff's fourth set of Data Request electronically filed by Hector Garcia-Santana on behalf of AEP Ohio Transmission Company, Inc.
07/22/2024 Staff Report of Investigation electronically filed by Ms. Allison Renick on behalf of Staff of OPSB.
06/28/2024 Response To Staff's 3rd Data Request. electronically filed by Hector Garcia-Santana on behalf of AEP Ohio Transmission Company, Inc.
06/18/2024 Response to Staff's Second Set of Data Request electronically filed by Hector Garcia-Santana on behalf of AEP Ohio Transmission Company, Inc.
05/29/2024 Response to Staff's 1st Set of Data Request electronically filed by Hector Garcia-Santana on behalf of AEP Ohio Transmission Company, Inc.
05/08/2024 Proof of Compliance electronically filed by Hector Garcia-Santana on behalf of AEP Ohio Transmission Company, Inc.
04/30/2024 Construction Notice of the South Coshocton-Wooster Line Rebuild Project Part 2 of 2 electronically filed by Hector Garcia-Santana on behalf of AEP Ohio Transmission Company, Inc.
04/30/2024 Construction Notice for the South Coshocton-Wooster Line Rebuild Project Part 1 of 2 electronically filed by Hector Garcia-Santana on behalf of AEP Ohio Transmission Company, Inc.
04/17/2024 In the Matter of the Pre-application Letter electronically filed by Hector Garcia-Santana on behalf of AEP Ohio Transmission Company, Inc.