06/25/2024
|
Correspondence regarding Condition No. 5 (Kirtland's Snake) in the Staff Report of Investigation electronically filed by Mr. Lawrence B. Hughes on behalf of American Transmission Systems, Inc. |
06/24/2024
|
Service Notice. |
06/24/2024
|
Staff Report of Investigation electronically filed by Mr. James S. O'Dell on behalf of Staff of OPSB. |
05/30/2024
|
Response to the First Set of Data Requests from the Staff of the Ohio Power Sitting Board for the Darrow-Hudson East 138 kV Transmission Line Structure Replacement and Addition Project electronically filed by Mr. Lawrence B. Hughes on behalf of American Transmission Systems, Inc. |
05/02/2024
|
Proof of Publication and Notice to Owners for the Darrow-Hudson East 138 kV Transmission Line Structure Replacement and Addition Project electronically filed by Mr. Lawrence B. Hughes on behalf of American Transmission Systems, Inc. |
04/29/2024
|
Letter of Notification for the Darrow-Hudson East 138 kV Transmission Line Structure Replacement and Addition Project (Part 7 of 7) electronically filed by Mr. Lawrence B. Hughes on behalf of American Transmission Systems, Inc. |
04/29/2024
|
Letter of Notification for the Darrow-Hudson East 138 kV Transmission Line Structure Replacement and Addition Project (Part 6 of 7) electronically filed by Mr. Lawrence B. Hughes on behalf of American Transmission Systems, Inc. |
04/29/2024
|
Letter of Notification for the Darrow-Hudson East 138 kV Transmission Line Structure Replacement and Addition Project (Part 5 of 7) electronically filed by Mr. Lawrence B. Hughes on behalf of American Transmission Systems, Inc. |
04/29/2024
|
Letter of Notification for the Darrow-Hudson East 138 kV Transmission Line Structure Replacement and Addition Project (Part 4 of 7) electronically filed by Mr. Lawrence B. Hughes on behalf of American Transmission Systems, Inc. |
04/29/2024
|
Letter of Notification for the Darrow-Hudson East 138 kV Transmission Line Structure Replacement and Addition Project (Part 3 of 7) electronically filed by Mr. Lawrence B. Hughes on behalf of American Transmission Systems, Inc. |
04/29/2024
|
Letter of Notification for the Darrow-Hudson East 138 kV Transmission Line Structure Replacement and Addition Project (Part 2 of 7) electronically filed by Mr. Lawrence B. Hughes on behalf of American Transmission Systems, Inc. |
04/29/2024
|
Letter of Notification for the Darrow-Hudson East 138 kV Transmission Line Structure Replacement and Addition Project (Part 1 of 7) electronically filed by Mr. Lawrence B. Hughes on behalf of American Transmission Systems, Inc. |
04/22/2024
|
Correspondence regarding the Amended Pre-Application Notification Letter (Expedited Treatment Requested) for the Darrow-Hudson East 138 kV Transmission Line Structure Replacement and Addition Project electronically filed by Mr. Lawrence B. Hughes on behalf of American Transmission Systems, Inc. |
04/09/2024
|
In the Matter of the Pre-Application Notification Letter for the Darrow-Hudson East 138 kV Transmission Line Structure Replacement and Addition Project electronically filed by Mr. Lawrence B. Hughes on behalf of American Transmission Systems, Inc. |