Date Filed | Summary | Pages |
05/01/2024 | Service Notice. | 1 |
05/01/2024 | Staff Report of Investigation electronically filed by Richard J. Gonzales on behalf of Staff of OPSB. | 7 |
03/12/2024 | Response of AEP Ohio Transmission Company to Staff's Data Request electronically filed by Hector Garcia-Santana on behalf of AEP Ohio Transmission Company, Inc.. | 6 |
02/15/2024 | Proof of Compliance Notices electronically filed by Hector Garcia-Santana on behalf of AEP Ohio Transmission Company, Inc. | 34 |
02/08/2024 | Construction Notice Application for the Melmore - Tiffin Center 138 kV Transmission Line Replacement Project electronically filed by Hector Garcia-Santana on behalf of AEP Ohio Transmission Company, Inc. | 69 |
02/07/2024 | In the Matter of the Pre-application Letter. electronically filed by Hector Garcia-Santana on behalf of AEP Ohio Transmission Company, Inc. | 2 |