12/05/2023
|
Service Notice - Staff Report. |
12/05/2023
|
Staff Report of Investigation electronically filed by Mr. Thomas J. Crawford on behalf of Staff of OPSB. |
11/16/2023
|
Notice of Response to Discovery request Ohio Power Siting Board Staff Second Set electronically filed by Hector Garcia-Santana on behalf of Ohio Power Company. |
11/01/2023
|
Response to Staff's First Set of Data Request electronically filed by Hector Garcia-Santana on behalf of AEP Ohio Transmission Company, Inc. |
09/20/2023
|
Correspondence regarding Proof of Compliance with the Jug Street-Corridor 345 kV Transmission Line Cut- in to Badger Station Project and Proof of Compliance with O.A.C. 4906-6-07 and 4906-6-08 electronically filed by Hector Garcia-Santana on behalf of AEP Ohio Transmission Company, Inc. |
09/13/2023
|
In the Matter of the Construction Notice Application for the Jug Street – Corridor 345 kV Transmission Line Cut-in to Badger Station Project electronically filed by Hector Garcia-Santana on behalf of AEP OhioTransmission Company, Inc. |