DIS - Case Record for 23-0576-EL-BNR Skip to main content
      
      
CASE NUMBER: 23-0576-EL-BNR
CASE DESCRIPTION: South Point – Portsmouth 138-kV Transmission Line Tie-in Project
DOCUMENT SIGNED ON: 4/28/2024
DATE OF SERVICE: ________________________________________
01/17/2024 Notification of Start of Construction electronically filed by Hector Garcia-Santana on behalf of AEP Ohio Transmission Company.
01/17/2024 Correspondence of Proof of Compliance with Condition (2) electronically filed by Hector Garcia-Santana on behalf of AEP Ohio Transmission Company.
08/14/2023 Service Notice- Staff Report.
08/14/2023 Staff Report of Investigation electronically filed by Mr. Grant T Zeto on behalf of Staff of the Ohio Power Siting Board.
08/03/2023 Response to Ohio Power Siting Board Staff's Discovery Request 1st Set for the South Point-Portsmouth Project electronically filed by Hector Garcia-Santana on behalf of AEP Ohio Transmission Company, Inc.
05/30/2023 Proof of Compliance electronically filed by Hector Garcia-Santana on behalf of AEP Ohio Transmission Company, Inc.
05/23/2023 In the Matter of the Construction Notice Application for the South Point-Portsmouth 138-kV Transmission Line Project electronically filed by Hector Garcia-Santana on behalf of AEP Ohio Transmission Company, Inc.