07/19/2023
|
Correspondence of Proof of Compliance with Condition electronically filed by Hector Garcia-Santana on behalf of AEP Ohio Transmission Company, Inc. |
06/30/2023
|
Notification of the Start of Construction for the Hillsboro-Milbrook Park 138 kV line Adjustment 2 Project electronically filed by Hector Garcia-Santana on behalf of AEP Ohio Transmission Company, Inc. |
06/15/2023
|
Service Notice. |
06/15/2023
|
Staff Report of Investigation electronically filed by Mr. Grant T. Zeto on behalf of Staff of the Ohio Power Siting Board and PUCO. |
06/06/2023
|
AEP Ohio Transmission Company, Inc Response to Ohio Power Siting Board Staff's 1st Set of Discovery Request electronically filed by Hector Garcia-Santana on behalf of AEP Ohio Transmission Company, Inc. |
06/06/2023
|
Notice of Proof of Compliance with the Notice Requirements electronically filed by Hector Garcia-Santana on behalf of AEP Ohio Transmission Company, Inc. |
05/31/2023
|
Construction Notice Application for the Hillsboro-Millbrook Park 138 kV Line Adjustment 2 Project electronically filed by Hector Garcia-Santana on behalf of AEP Ohio Transmission Company, Inc. |
05/19/2023
|
In the Matter of the Pre-application Letter Hillsboro Millbrook, electronically filed by Hector Garcia-Santana on behalf of AEP Ohio Transmission Company, Inc. |