05/28/2024
|
Notice of Construction Completeness Letter for the Highland – Magellan No. 1 138 kV Transmission Line Structure Replacement Project electronically filed by Mr. Lawrence B. Hughes on behalf of American Transmission Systems, Inc. |
06/14/2023
|
Service Notice. |
06/14/2023
|
Staff Report of Investigation electronically filed by Mr. Jess Stottsberry on behalf of Staff of OPSB. |
05/30/2023
|
Response to First Set of Data Requests from Staff electronically filed by Ms. Devan K. Flahive on behalf of American Transmission Systems Incorporated. |
05/25/2023
|
Notice of Proof of Payment for Expedited Review filed by Michael A. DeSarro on behalf of American Transmission Systems, Inc. |
05/23/2023
|
Construction Notice Highland-Magellan No. 1 138kV Transmission Line Structure Replacement Project electronically filed by Ms. Devan K. Flahive on behalf of American Transmission Systems Incorporated. |
05/16/2023
|
In the Matter of the Pre-Application Notification Letter for the Highland-Magellan No. 1 138kV Transmission Line Structure Replacement Project electronically filed by Ms. Devan K. Flahive on behalf of American Transmission Systems Incorporated. |