CASE NUMBER: 23-0141-EL-BLN
CASE DESCRIPTION: Holloway-Knox 138 kV Transmission Line Rebuild Project - Holloway Sub to Nottingham Sub Segment
DOCUMENT SIGNED ON: 4/30/2024
DATE OF SERVICE: ________________________________________
09/11/2023 Notice of Substitution of Counsel electronically filed by Ms. Devan K. Flahive on behalf of American Transmission Systems Incorporated.
06/09/2023 Notice of Updated Construction Start Date electronically filed by Ms. Devan K. Flahive on behalf of AmericanTransmission Systems Incorporated.
06/01/2023 Notice of Compliance with Construction Certificate Condition (3) - Belmont County Floodplain Permit electronically filed by Ms. Devan K. Flahive on behalf of AmericanTransmission Systems Incorporated.
05/23/2023 Notice Construction Commencement electronically filed by Ms. Devan K. Flahive on behalf of American Transmission Systems Incorporated.
05/12/2023 Service Notice.
05/11/2023 Staff Report of Investigation electronically filed by Mr. James S. O'Dell on behalf of Staff of OPSB.
04/20/2023 Response to Staff's First Data Request electronically filed by Ms. Devan K. Flahive on behalf of American Transmission Systems Incorporated.
03/16/2023 Proof of Publication and Public Notice Letters electronically filed by Mr. Christopher K. Riedel on behalf of American Transmission Systems Incorporated.
02/28/2023 Application, Letter of Notification, Part 5 of 5, electronically filed by Mr. Christopher K. Riedel on behalf of American Transmission Systems Incorporated.
02/28/2023 Application, Letter of Notification, Part 4 of 5, electronically filed by Mr. Christopher K. Riedel on behalf of American Transmission Systems Incorporated.
02/28/2023 Application, Letter of Notification, Part 3 of 5, electronically filed by Mr. Christopher K. Riedel on behalf of American Transmission Systems Incorporated.
02/28/2023 Application, Letter of Notification, Part 2 of 5, electronically filed by Mr. Christopher K. Riedel on behalf of American Transmission Systems Incorporated.
02/28/2023 Application, Letter of Notification, Part 1 of 5, electronically filed by Mr. Christopher K. Riedel on behalf of American Transmission Systems Incorporated.
02/22/2023 Corrected Pre-Application Notification Letter for the Holloway - Knox 138 kV Transmission Line Rebuild Project - Holloway Substation to Nottingham Substation Segment electronically filed by Ms. Devan K. Flahive on behalf of American Transmission Systems Incorporated.
02/17/2023 In the Matter of the Pre-Application Notification Letter for Holloway-Knox 138 kV Transmission Line Rebuild Project electronically filed by Mr. Christopher K. Riedel on behalf of American Transmission Systems Incorporated.