DIS - Case Record for 23-0104-EL-BLN Skip to main content
      
      
CASE NUMBER: 23-0104-EL-BLN
CASE DESCRIPTION: In the Matter of the Letter of Notification Application for the Blossom Solar 138 kV Gen-Tie Transmission Line Project
DOCUMENT SIGNED ON: 11/21/2024
DATE OF SERVICE: ________________________________________
09/20/2024 Notice of Certificate Compliance with Condition 40 – Final Complaint Resolution Plan electronically filed by Christine M.T. Pirik on behalf of Blossom Solar, LLC.
09/05/2024 Notice of Certificate Compliance Condition 22 regarding Update to Decommissioning Plan filed on March 29, 2024 electronically filed by Christine M.T. Pirie on behalf of Blossom Solar, LLC.
03/29/2024 Notice - Certificate Compliance Condition 22 – Decommissioning Plan electronically filed by Christine M.T. Pirik on behalf of Blossom Solar, LLC.
07/20/2023 Service Notice.
07/20/2023 Opinion, Order, and Certificate that the Ohio Power Siting Board determines that a certificate should be issued to Blossom Solar, LLC for the construction, operation, and maintenance of the 138 kilovolt transmission line in Morrow County electronically filed by Ms. Donielle M. Hunter on behalf of Ohio Power Siting Board.
06/28/2023 Notice of Withdrawal of Counsel electronically filed by Ms. Anna Sanyal on behalf of Blossom Solar, LLC.
06/21/2023 Service Notice.
06/21/2023 Administrative Law Judge Entry granting Applicant's motion for waiver and suspending the automatic approval process electronically filed by Debbie S. Ryan on behalf of Nicholas J. Walstra, Administrative Law Judge, Ohio Power Siting Board.
06/20/2023 Amended Staff Report of Investigation electronically filed by Mr. James S. O'Dell on behalf of Staff of OPSB.
06/20/2023 Motion for Waiver and Objection electronically filed by Mr. Matthew C. McDonnell on behalf of Blossom Solar, LLC.
06/20/2023 Notice of Appearance of Counsel for Blossom Solar, LLC electronically filed by Mr. Matthew C. McDonnell on behalf of Blossom Solar, LLC.
06/14/2023 Service Notice.
06/14/2023 Staff Report of Investigation electronically filed by Mr. James S. O'Dell on behalf of Staff of OPSB.
05/03/2023 Correspondence Regarding Denial of Expedited Treatment electronically filed by Mr. Jason Cross on behalf of Staff of OPSB.
04/20/2023 Proof of Publication and Proof of Compliance electronically filed by Ms. Anna Sanyal on behalf of Blossom Solar, LLC.
04/13/2023 Letter of Notification Application for the Blossom Solar, LLC 138 kV Transmission Line Project electronically filed by Ms. Anna Sanyal on behalf of Blossom Solar, LLC.
04/06/2023 In the Matter of the Pre-Application Notification Letter electronically filed by Ms. Anna Sanyal on behalf of Blossom Solar, LLC.