CASE NUMBER: 22-1027-EL-BNR
CASE DESCRIPTION: Ohio Central-Fostoria 345 kV Transmission Line Adjustment Project
DOCUMENT SIGNED ON: 4/26/2024
DATE OF SERVICE: ________________________________________
01/27/2023 Service Notice (Staff Report).
01/27/2023 Staff Report of Investigation electronically filed by Mr. Thomas J. Crawford on behalf of Staff of OPSB.
11/21/2022 Notice of Proof of Compliance electronically filed by Hector Garcia-Santana on behalf of Ohio Power Company.
11/04/2022 In the Matter of the Construction Notice Application for the Fostoria Central 345kV Transmission Line Adjustment Project, Ohio Central - Fostoria electronically filed by Hector Garcia-Santana on behalf of Ohio Power Company.