CASE NUMBER: 22-0856-EL-BTX
CASE DESCRIPTION: New Liberty - East Leipsic 138 kV Upgrade Project
DOCUMENT SIGNED ON: 4/26/2024
DATE OF SERVICE: ________________________________________
10/19/2023 Service Notice.
10/19/2023 Opinion & Order approves the stipulation and recommendation filed by the parties and issues a certificate of environmental compatibility and public need to AEP Ohio Transmission Company, Inc. for the construction, operation, and maintenance of the new Liberty-East Leipsic 138 kilovolt transmission line upgrade project along the preferred route, subject to the conditions set forth in this Opinion and Order electronically filed by Debbie S. Ryan on behalf of Ohio Power Siting Board.
09/21/2023 Notice of Withdrawal of Counsel Robert Eubanks (0073386) electronically filed by Mrs. Kimberly M. Naeder on behalf of PUCO.
08/11/2023 Transcript of Hearing held on Tuesday July 25th 2023, at 10:00AM, before the Honorable Isabel Marcelletti, at the offices of the Public Utilities Commission of Ohio, 180 East Broad Street, Hearing Room 11-C, Columbus, Ohio electronically filed by Mr. Ken Spencer on behalf of Armstrong & Okey, Inc. and Spencer, Michael O. Mr.
07/26/2023 Public Hearing Exhibit 1 for hearing held on Tuesday, July 11, 2023 electronically filed by Litigation Support on behalf of Public Utilities Commission of Ohio.
07/26/2023 Transcript for the hearing held on Tuesday, July 11, 2023 at 5:01 p.m. at the McComb Public Library, 113 S. Todd St, McComb, OH 45858 before Administrative Law Judges Matthew Sandor and Isabel M. Marcelletti electronically filed by Litigation Support on behalf of Public Utilities Commission of Ohio.
07/25/2023 Public Comment of Donna Kelley.
07/24/2023 Pre-filed Testimony of Mark Bellamy, on Behalf of The Staff of The Public Utilities Commission of Ohio, Power Siting Department electronically filed by Mrs. Kimberly M. Naeder on behalf of OPSB.
07/24/2023 Pre-Filed Testimony of David Binger, electronically filed by Hector Garcia-Santana on behalf of AEP Ohio Transmission Company, Inc.
07/24/2023 Stipulation and Recommendation, electronically filed by Hector Garcia-Santana on behalf of AEP Ohio Transmission Company, Inc.
07/17/2023 Service Notice.
07/17/2023 Administrative Law Judge Entry granting AEP Ohio Transco’s motion for leave to file a late-file motion and motion for an extension, as set forth in Paragraph 12, electronically filed by Debbie S. Ryan on behalf of Matthew J. Sandor, Administrative Law Judge, Ohio Power Siting Board.
07/14/2023 Motion For Extension/Motion for Leave to File Leave to File Late-Filed Motion and Memorandum in Support electronically filed by Hector Garcia-Santana on behalf of AEP Ohio Transmission Company, Inc.
07/13/2023 Notice of Proof of Compliance with the New Liberty-East Leipsic 138 kV Upgrade Project electronically filed by Hector Garcia-Santana on behalf of AEP Ohio Transmission Company, Inc.
07/03/2023 Notice of Proof of Compliance with Service Requirements electronically filed by Hector Garcia-Santana on behalf of AEP Ohio Transmission Company, Inc.
06/26/2023 Service Notice.
06/26/2023 Staff Report of Investigation electronically filed by Mark C. Bellamy on behalf of OPSB Staff.
06/20/2023 Response To Staff's 4th Set of Data Request electronically filed by Hector Garcia-Santana on behalf of AEP Ohio Transmission Company, Inc.
06/08/2023 Supplemental Information in Response to Staff's 3rd Data Request. electronically filed by Hector Garcia-Santana on behalf of AEP Ohio Transmission Company, Inc.
05/05/2023 Response to Staff's 3rd Set of Discovery Request electronically filed by Hector Garcia-Santana on behalf of AEP Ohio Transmission Company, Inc.
04/24/2023 Service Notice.
04/24/2023 Administrative Law Judge Entry ordering that the effective date of the application be April 24, 2023, setting a local public hearing on July 11, 2023, at 5:00 p.m., at the McComb Library, 113 South Todd Street, McComb, Ohio 45858, ordering that an adjudicatory hearing commence on July 25, 2023, at 10:00 a.m., at the offices of the Public Utilities Commission of Ohio, 180 East Broad Street, 11th Floor, Hearing Room 11-C, Columbus, Ohio 43215-3793, ordering that notices of the application and hearings be issued by AEP Ohio Transco in accordance with Paragraphs 10 and 11 and ordering that the parties observe the filing deadlines set forth in Paragraph 12 electronically filed by Debbie S. Ryan on behalf of Matthew J. Sandor, Administrative Law Judge, Ohio Power Siting Board.
04/20/2023 Notice of Proof of Payment electronically filed by Hector Garcia-Santana on behalf of AEP Ohio Transmission Company, Inc.
04/12/2023 Response filed by Robert E Feighner, Jr. on behalf of the Village of McComb.
03/21/2023 Proof of Compliance with O.A.C. 4906-3-07 electronically filed by Hector Garcia-Santana on behalf of AEP OhioTransmission Company, Inc.
03/03/2023 Correspondence Letter regarding application completeness electronically filed by Mr. Matt Butler on behalf of Staff of OPSB.
03/03/2023 Discovery Responses of AEP Ohio Transmission Company to OPSB Staff's Second Discovery Request electronically filed by Hector Garcia-Santana on behalf of AEP Ohio Transmission Company, Inc.
02/21/2023 Response to Staff's First Set of Discovery Request electronically filed by Hector Garcia-Santana on behalf of AEP Ohio Transmission Company, Inc.
01/04/2023 Application (Part 3) electronically filed by Hector Garcia-Santana on behalf of AEP Ohio Transmission Company, Inc.
01/04/2023 Application (Part 2) electronically filed by Hector Garcia-Santana on behalf of AEP Ohio Transmission Company, Inc.
01/04/2023 Application for Certificate of Environmental Compatibility and Public Need for New Liberty- East Leipsic 138-kv Upgrade Project (Part 1) electronically filed by Hector Garcia-Santana on behalf of AEP Ohio Transmission Company, Inc.
01/04/2023 Cover Letter electronically filed by Hector Garcia-Santana on behalf of AEP Ohio Transmission Company, Inc.
10/21/2022 Notice of Proof of Compliance with the Notice Requirements electronically filed by Hector Garcia-Santana on behalf of AEP Ohio Transmission Company, Inc.
09/19/2022 In the Matter of the Pre-Application Notification Letter for the AEP Ohio Transmission Company for a Certificate of Environmental Compatibility and Public Need for the New Liberty- East Leipsic 138kV Upgrade Project electronically filed by Hector Garcia Santana on behalf of AEP Ohio Transmission Company, Inc.