06/13/2023 Notification of In-Service Date for the Nottingham Solar 138kV Transmission Line Project electronically filed by Hector Garcia-Santana on behalf of AEP Ohio Transmission Company, Inc.
03/06/2023 Start of Construction Notification electronically filed by Hector Garcia-Santana on behalf of AEP Ohio Transmission Company, Inc.
10/19/2022 Notice of Proof of Compliance with Condition 3 electronically filed by Hector Garcia-Santana on behalf of AEP Ohio Transmission Company, Inc.
10/07/2022 Service Notice (Staff Report).
10/07/2022 Staff Report of Investigation electronically filed by Mr. Matt Butler on behalf of Staff of OPSB.
10/04/2022 Supplemental Information Regarding Construction Notice electronically filed by Hector Garcia-Santana on behalf of AEP Ohio Transmission Company, Inc.
09/23/2022 Construction Notice Application for the Nottingham - Nottingham Solar 138 kV Transmission Line Project electronically filed by Hector Garcia-Santana on behalf of AEP Ohio Transmission Company, Inc.
09/21/2022 In the Matter of the Pre-Application Notification Letter for the Nottingham-Nottingham Solar 138 kV Transmission Line Project electronically filed by Hector Garcia-Santana on behalf of AEP Ohio Transmission Company, Inc..