DIS - Case Record for 22-0597-EL-BLN Skip to main content
      
      
CASE NUMBER: 22-0597-EL-BLN
CASE DESCRIPTION: Midway-Richland-Wauseon 138 kV Transmission Line Three Terminal Line Elimination Project
DOCUMENT SIGNED ON: 9/19/2024
DATE OF SERVICE: ________________________________________
03/10/2023 Letter of Notification of Construction Completion electronically filed by Mr. Christopher K. Riedel on behalf of American Transmission Systems Incorporated.
11/15/2022 Public Comment of Cody Damman; Mark, Mick, Denise and Tamara Nofziger; and Kim and Kevin Demaline filed by Jan Stamm.
11/14/2022 Public Comment of Cody Damman; Mark, Mick, Denise & Tamara Nofziger; and Kim and Kevin Demaline filed by Jan H. Stamm.
10/19/2022 Notice Compliance Filing: Permits electronically filed by Ms. Devan K. Flahive on behalf of American Transmission Systems Incorporated.
09/09/2022 Service Notice - Staff Report.
09/09/2022 Notice of Construction Start electronically filed by Ms. Devan K. Flahive on behalf of American Transmission Systems Incorporated.
09/08/2022 Staff Report of Investigation electronically filed by Mr. Matt Butler on behalf of Staff of OPSB.
08/22/2022 Revisions to Tables Regarding Transmission Line Loading and EMF Calculations electronically filed by Ms. Devan K. Flahive on behalf of American Transmission Systems Incorporated.
08/22/2022 Supplemental Response to Second Set of Data Requests From OPSB Staff electronically filed by Ms. Devan K. Flahive on behalf of American Transmission Systems Incorporated.
08/12/2022 Response to Second Set of Data Requests electronically filed by Ms. Devan K. Flahive on behalf of American Transmission Systems Incorporated.
08/08/2022 Proof of Publication and Public Notice Letters electronically filed by Ms. Devan K. Flahive on behalf of American Transmission Systems Incorporated.
08/05/2022 Response to OPSB Staff's First Set of Data Requests electronically filed by Ms. Devan K. Flahive on behalf of American Transmission Systems Incorporated.
07/27/2022 Midway-Richland-Wauseon 138 kv Transmission Line Three Terminal Line Elimination Project Letter of Notification electronically filed by Ms. Devan K. Flahive on behalf of American Transmission Systems Incorporated.
06/16/2022 In the Matter of the Pre-Application Notification Letter for the Midway-Richland-Wauseon 138 kV Transmission Line Three Terminal Line Elimination Project electronically filed by Ms. Devan K. Flahive on behalf of American Transmission Systems Incorporated.