05/10/2023 Notification of In-Service Date for the East Amsterdam-Carroll Co-Op 138 kV Transmission Line Project electronically filed by Hector Garcia-Santana on behalf of AEP Ohio Transmission Company, Inc.
03/31/2023 Notification of Start of Construction electronically filed by Hector Garcia-Santana on behalf of AEP Ohio Transmission Company, Inc.
01/23/2023 Notice of Proof of Compliance with Condition 2 electronically filed by Hector Garcia-Santana on behalf of AEP Ohio Transmission Company, Inc.
11/10/2022 Notice of Proof of Compliance with Condition 2 electronically filed by Hector Garcia-Santana on behalf of AEP Ohio Transmission Company, Inc.
11/03/2022 Service Notice - Staff Report.
11/03/2022 Staff Report of Investigation electronically filed by Allison DeLong on behalf of Staff of OPSB.
09/13/2022 Proof of Compliance, East Amsterdam-Carroll electronically filed by Hector Garcia-Santana on behalf of AEP Ohio Transmission Company, Inc.
08/12/2022 Construction Notice Application for the East Amsterdam-Carroll Co-op 138 kV Transmission Line Project electronically filed by Hector Garcia-Santana on behalf of AEP Ohio Transmission Company, Inc.