05/10/2023
|
Notification of In-Service Date for the East Amsterdam-Carroll Co-Op 138 kV Transmission Line Project electronically filed by Hector Garcia-Santana on behalf of AEP Ohio Transmission Company, Inc. |
03/31/2023
|
Notification of Start of Construction electronically filed by Hector Garcia-Santana on behalf of AEP Ohio Transmission Company, Inc. |
01/23/2023
|
Notice of Proof of Compliance with Condition 2 electronically filed by Hector Garcia-Santana on behalf of AEP Ohio Transmission Company, Inc. |
11/10/2022
|
Notice of Proof of Compliance with Condition 2 electronically filed by Hector Garcia-Santana on behalf of AEP Ohio Transmission Company, Inc. |
11/03/2022
|
Service Notice - Staff Report. |
11/03/2022
|
Staff Report of Investigation electronically filed by Allison DeLong on behalf of Staff of OPSB. |
09/13/2022
|
Proof of Compliance, East Amsterdam-Carroll electronically filed by Hector Garcia-Santana on behalf of AEP Ohio Transmission Company, Inc. |
08/12/2022
|
Construction Notice Application for the East Amsterdam-Carroll Co-op 138 kV Transmission Line Project electronically filed by Hector Garcia-Santana on behalf of AEP Ohio Transmission Company, Inc. |
08/08/2022
|
In the Matter of the Pre-Application Letter of East Amsterdam-Carroll electronically filed by Hector Garcia-Santana on behalf of AEP Ohio Transmission Company. |