CASE NUMBER: 22-0512-EL-BNR
CASE DESCRIPTION: Cyprus 138 kV Extension Adjustment Project
DOCUMENT SIGNED ON: 4/24/2024
DATE OF SERVICE: ________________________________________
06/03/2022 Notice of Proof of Compliance with Condition 1 electronically filed by Hector Garcia-Santana on behalf of AEP Ohio Transmission Company, Inc.
05/27/2022 Service Notice.
05/27/2022 Staff Report of Investigation electronically filed by Mr. Matt Butler on behalf of Staff of OPSB.
05/24/2022 Notice of Proof of Compliance with the Notice Requirements electronically filed by Hector Garcia-Santana on behalf of AEP Ohio Transmission Company, Inc.
05/18/2022 Construction Notice for the Cyprus138 kV Extension Adjustment Project electronically filed by Hector Garcia-Santana on behalf of APE Ohio Transmission Company, Inc.
05/11/2022 In the Matter of the Pre-Application Notification Letter electronically filed by Hector Garcia-Santana on behalf of AEP Ohio Transmission Company, Inc.