DIS - Case Record for 22-0445-EL-BNR Skip to main content
      
      
CASE NUMBER: 22-0445-EL-BNR
CASE DESCRIPTION: Duke Energy Ohio, Inc.
DOCUMENT SIGNED ON: 4/24/2024
DATE OF SERVICE: ________________________________________
12/19/2022 Notification of Completion of Construction and In-Service Date electronically filed by Ms. Emily Olive on behalf of Duke Energy Ohio and D'Ascenzo, Rocco O. Mr. and Kingery, Jeanne W. Ms. and Vaysman, Larisa M. Ms. and Akhbari, Elyse H. Ms.
05/13/2022 Correspondence regarding the State Route 63 Transmission Line Relocation Northern Harris, Condition 4 electronically filed by Mrs. Tammy M. Meyer on behalf of Duke Energy Ohio Inc., D'Ascenzo, Rocco, Kingery, Jeanne W., Akhbari, Elyse Hanson and Vaysman, Larisa.
05/10/2022 Letter Accepting Staff's Conditions electronically filed by Ms. Emily Olive on behalf of Duke Energy Ohio, D'Ascenzo, Rocco O. Mr., Kingery, Jeanne W. Ms. and Akhbari, Elyse H. Ms.
05/06/2022 Service Notice.
05/06/2022 Staff Report of Investigation electronically filed by Mr. Matt Butler on behalf of Staff of OPSB.
05/03/2022 Notice of Proof of Service electronically filed by Mrs. Tammy M. Meyer on behalf of Duke Energy Ohio Inc., D'Ascenzo, Rocco, Kingery, Jeanne W. and Akhbari, Elyse Hanson.
04/27/2022 Construction Notice For The State Route 63 Transmission Line Relocation Duke Energy Ohio, Inc. electronically filed by Mrs. Tammy M. Meyer on behalf of Duke Energy Ohio Inc. and D'Ascenzo, Rocco and Kingery, Jeanne W. and Vaysman, Larisa and Akhbari, Elyse Hanson.
04/22/2022 In the Matter of the Pre-Application Notification Letter in accordance with O.A.C. 4906-6-03(A) electronically filed by Mrs. Tammy M. Meyer on behalf of Duke Energy Ohio Inc. and D'Ascenzo, Rocco and Kingery, Jeanne W.