01/24/2023
|
Notice of In- Service Date for the West Moulton- Amsterdam 138 kV Transmission Line Project electronically filed by Hector Garcia-Santana on behalf of AEP Ohio Transmission Company, Inc. |
09/19/2022
|
Notice of Start of Construction for the West Moulton-Amsterdam Project electronically filed by Hector Garcia-Santana on behalf of AEP Ohio Transmission Company, Inc. |
09/14/2022
|
Proof of Compliance with Condition (3) electronically filed by Hector Garcia-Santana on behalf of AEP Ohio Transmission Company, Inc. |
06/21/2022
|
Service Notice (Staff Report) |
06/21/2022
|
Staff Report of Investigation electronically filed by Mr. Matt Butler on behalf of Staff of OPSB |
04/04/2022
|
Proof of Compliance electronically filed by Hector Garcia-Santana on behalf of AEP OhioTransmission Company, Inc. |
03/29/2022
|
Construction Notice Application for West Moulton-Amsterdam 138kV Transmission Line Project electronically filed by Hector Garcia-Santana on behalf of AEP Ohio Transmission Company, Inc. |
03/29/2022
|
In the Matter of the Pre-Application Notification Letter for the West Moulton-Amsterdam 138kV Transmission Line Project electronically filed by Hector Garcia-Santana on behalf of AEP Ohio Transmission Company, Inc. |