Skip to main content
      
      
CASE NUMBER: 21-1206-EL-BLN
CASE DESCRIPTION: Crooksville-North Newark 138-kV Transmission Line Rebuild Project (Newark Center-Crooksville)
DOCUMENT SIGNED ON: 9/29/2022
DATE OF SERVICE: ________________________________________
02/24/2022 Service Notice (Staff Report).
02/24/2022 Staff Report of Investigation electronically filed by Mr. Matt Butler on behalf of Staff of OPSB.
12/02/2021 Letter of Notification Part 10 electronically filed by Hector Garcia-Santana on behalf of AEP Ohio Transmission Company, Inc..
12/02/2021 Letter of Notification Part 9 electronically filed by Hector Garcia-Santana on behalf of AEP Ohio Transmission Company, Inc.
12/02/2021 Letter of Notification Part 8 electronically filed by Hector Garcia-Santana on behalf of AEP Ohio Transmission Company, Inc.
12/02/2021 Letter of Notification Part 7 electronically filed by Hector Garcia-Santana on behalf of AEP Ohio Transmission Company, Inc.
12/02/2021 Letter of Notification Part 6 electronically filed by Hector Garcia-Santana on behalf of AEP Ohio Transmission Company, Inc.
12/02/2021 Letter of Notification Part 5 electronically filed by Hector Garcia-Santana on behalf of AEP Ohio Transmission Company, Inc.
12/02/2021 Letter of Notification Part 4 electronically filed by Hector Garcia-Santana on behalf of APE Ohio Transmission Company, Inc.
12/02/2021 Letter of Notification Part 3 electronically filed by Hector Garcia-Santana on behalf of AEP Ohio Transmission Company, Inc.
12/02/2021 Letter of Notification Part 2 electronically filed by Hector Garcia-Santana on behalf of AEP Ohio Transmission Company, Inc.
12/02/2021 In the Matter of the Letter of Notification Part 1 electronically filed by Hector Garcia-Santana on behalf of AEP Ohio Transmission Company, Inc.