10/07/2024 Correspondence Letter regarding the Construction and Operation update electronically filed by Mr. Michael J. Settineri on behalf of Big Plan Solar LLC.
08/09/2024 Public Comment of Karen Kindel and Dan Cavlina.
07/22/2024 Public Comment of James Reed.
09/22/2022 Notice of Compliance with Certificate Condition #8 (Part 15) - Detailed Engineering Drawings electronically filed by Mr. Joseph D. Jordan on behalf of Big Plain Solar, LLC.
09/22/2022 Notice of Compliance with Certificate Condition #8 (Part 14) - Detailed Engineering Drawings electronically filed by Mr. Joseph D. Jordan on behalf of Big Plain Solar, LLC.
09/22/2022 Notice of Compliance with Certificate Condition #8 (Part 13) - Detailed Engineering Drawings electronically filed by Mr. Joseph D. Jordan on behalf of Big Plain Solar, LLC.
09/22/2022 Notice of Compliance with Certificate Condition #8 (Part 12) - Detailed Engineering Drawings electronically filed by Mr. Joseph D. Jordan on behalf of Big Plain Solar, LLC.
09/22/2022 Notice of Compliance with Certificate Condition #8 (Part 11) - Detailed Engineering Drawings electronically filed by Mr. Joseph D. Jordan on behalf of Big Plain Solar, LLC.
09/22/2022 Notice of Compliance with Certificate Condition #8 (Part 10) - Detailed Engineering Drawings electronically filed by Mr. Joseph D. Jordan on behalf of Big Plain Solar, LLC.
09/22/2022 Notice of Compliance with Certificate Condition #8 (Part 9) - Detailed Engineering Drawings electronically filed by Mr. Joseph D. Jordan on behalf of Big Plain Solar, LLC.
09/22/2022 Notice of Compliance with Certificate Condition #8 (Part 8) - Detailed Engineering Drawings electronically filed by Mr. Joseph D. Jordan on behalf of Big Plain Solar, LLC.
09/22/2022 Notice of Compliance with Certificate Condition #8 (Part 7) - Detailed Engineering Drawings electronically filed by Mr. Joseph D. Jordan on behalf of Big Plain Solar, LLC.
09/22/2022 Notice of Compliance with Certificate Condition #8 (Part 6) - Detailed Engineering Drawings electronically filed by Mr. Joseph D. Jordan on behalf of Big Plain Solar, LLC.
09/22/2022 Notice of Compliance with Certificate Condition #8 (Part 5) - Detailed Engineering Drawings electronically filed by Mr. Joseph D. Jordan on behalf of Big Plain Solar, LLC.
09/22/2022 Notice of Compliance with Certificate Condition #8 (Part 4) - Detailed Engineering Drawings electronically filed by Mr. Joseph D. Jordan on behalf of Big Plain Solar, LLC.
09/22/2022 Notice of Compliance with Certificate Condition #8 (Part 3) - Detailed Engineering Drawings electronically filed by Mr. Joseph D. Jordan on behalf of Big Plain Solar, LLC.
09/22/2022 Notice of Compliance with Certificate Condition #8 (Part 2) - Detailed Engineering Drawings electronically filed by Mr. Joseph D. Jordan on behalf of Big Plain Solar, LLC.
09/22/2022 Notice of Compliance with Certificate Condition #8 (Part 1) - Detailed Engineering Drawings electronically filed by Mr. Joseph D. Jordan on behalf of Big Plain Solar, LLC.
09/22/2022 Notice of Compliance with Certificate Condition #8 - Filing of Detailed Engineering Drawings electronically filed by Mr. Joseph D. Jordan on behalf of Big Plain Solar, LLC.
06/10/2022 Notice of Compliance with Certificate Condition electronically filed by Mr. Joseph D Jordan on behalf of Big Plain Solar, LLC
02/17/2022 Service Notice.
02/17/2022 Order on Certificate granting the application filed by Big Plain Solar, LLC to amend its certificate for its Madison Solar Farm Project in order to add an Operations and Maintenance building, an additional 0.45-mile access road, and a change in fencing from chain link to a form of wildlife fencing for the electric generating facility in Madison County, Ohio electronically filed by Ms. Mary E. Fischer on behalf of Ohio Power Siting Board.
01/28/2022 Service Notice.
01/28/2022 Staff Report of Investigation electronically filed by Mr. Matt Butler on behalf of Staff of OPSB.
12/07/2021 Proof of Publication of Public Notice of Application electronically filed by Ms. Anna Sanyal on behalf of Big Plain Solar, LLC.
11/29/2021 Public Comment of Alisa DeMatteo, via website, electronically filed by Docketing Staff.
11/24/2021 Notice of Proof of Service of First Amendment Application electronically filed by Ms. Anna Sanyal on behalf of Big Plain Solar, LLC.
11/24/2021 In the Matter of the First Amendment Application of Big Plain Solar, LLC for its Madison Solar Farm Project electronically filed by Ms. Anna Sanyal on behalf of Big Plain Solar, LLC.