CASE NUMBER: 21-1084-EL-BLN
CASE DESCRIPTION: Arboles 138 kV Station Project
DOCUMENT SIGNED ON: 4/30/2024
DATE OF SERVICE: ________________________________________
08/08/2022 Proof of Compliance electronically filed by Hector Garcia-Santana on behalf of AEP Ohio Transmission Company, Inc.
03/22/2022 Notification of Start of Construction electronically filed by Hector Garcia-Santana on behalf of AEP Ohio Transmission Company, Inc.
03/07/2022 Service Notice.
03/07/2022 Staff Report of Investigation electronically filed by Mr. Matt Butler on behalf of Staff of OPSB.
12/27/2021 Proof of Compliance with O.A.C. 4906-6-07 and 4906-6-08 electronically filed by Hector Garcia-Santana on behalf of AEP Ohio Transmission Company, Inc.
12/13/2021 Application Letter of Notification Part 2 electronically filed by Hector Garcia-Santana on behalf of AEP Ohio Transmission Company, Inc.
12/13/2021 Application Letter of Notification Part 1 electronically filed by Hector Garcia-Santana on behalf of AEP Ohio Transmission Company, Inc.