DIS - Case Record for 21-0979-EL-BNR Skip to main content

Case Record For:

21-0979-EL-BNR

File a Public Comment
Case Title: Fostoria – East Lima 138 kV Transmission Line Tie-Ins to North Woodcock Station Project
Status: OPEN-OPEN
Industry Code: EL-ELECTRIC
Purpose Code: BNR-Construction notification report
Date Opened: 9/21/2021
Date Closed:
Printable Docket Card Service List
View per page
Date FiledSummaryPages
04/12/2022Notice of Proof of Compliance with Condition No. 2 electronically filed by Hector Garcia-Santana on behalf of Ohio Power Company.170
04/12/2022Notification of Start of Construction electronically filed by Hector Garcia-Santana on behalf of Ohio Power Company.2
12/20/2021Service Notice - Staff Report.2
12/20/2021Staff Report of Investigation electronically filed by BreAnna J. Freeman on behalf of Staff of OPSB.5
10/07/2021Notice of Proof of Compliance with Notice Requirements electronically filed by Hector Garcia-Santana on behalf of AEP Ohio Transmission Company, Inc.30
09/29/2021Construction Notice Application for the Fostoria – East Lima 138 kV Cut-In for North Woodcock Station Project electronically filed by Hector Garcia-Santana on behalf of Ohio Power Company.83
09/21/2021In the Matter of the Pre-Application Notification Letter of Ohio Power Company for a Certificate of Environmental Compatibility and Public Need for the Fostoria – East Lima 138 kV Cut-In for North Woodcock Station Project electronically filed by Hector Garcia-Santana on behalf of Ohio Power Company.2