CASE NUMBER: 21-0850-EL-BLN
CASE DESCRIPTION: Bixby-Shannon 138 kV Transmission Line Rebuild Project
DOCUMENT SIGNED ON: 7/17/2024
DATE OF SERVICE: ________________________________________
04/11/2022 Proof of Compliance electronically filed by Hector Garcia-Santana on behalf of AEP Ohio Transmission Company, Inc.
02/28/2022 Proof of Compliance with Condition (2) electronically filed by Hector Garcia-Santana on behalf of AEP Ohio Transmission Company, Inc.
02/25/2022 Proof of Compliance with Condition electronically filed by Hector Garcia-Santana on behalf of AEP Ohio Transmission Company, Inc.
02/16/2022 Notice Proof of Compliance with Condition 3 electronically filed by Hector Garcia-Santana on behalf of AEP Ohio Transmission Company, Inc.
02/16/2022 Proof of Compliance with Condition electronically filed by Hector Garcia-Santana on behalf of AEP Ohio Transmission Company, Inc.
02/16/2022 Notification of Start of Construction electronically filed by Hector Garcia-Santana on behalf of AEP Ohio Transmission Company, Inc.
12/10/2021 Service Notice - Staff Report.
12/10/2021 Staff Report of Investigation electronically filed by Mr. Matt Butler on behalf of Staff of OPSB.
10/28/2021 Proof of Compliance electronically filed by Hector Garcia-Santana on behalf of AEP Ohio Transmission Company, Inc.
09/17/2021 Letter of Notification Application - Part 2 electronically filed by Hector Garcia-Santana on behalf of AEP Ohio Transmission Company, Inc.
09/17/2021 Letter of Notification Application - Part 1 electronically filed by Hector Garcia-Santana on behalf of AEP Ohio Transmission Company, Inc.
09/14/2021 In the Matter of the Pre-Application Notification Letter of AEP Ohio Transmission Company Inc. for a Certificate of Environmental Compatibility and Public Need for the Bixby-Shannon 138kV Transmission Line Rebuild Project electronically filed by Hector Garcia-Santana on behalf of AEP Ohio Transmission Company, Inc.