09/11/2024
|
Notice of Proof of Compliance, Notification Letters of 3rd Amendment electronically filed by Hector Garcia-Santana on behalf of AEP Ohio Transmission Company.
|
03/11/2022
|
Notice of Proof of Compliance with Condition 9 electronically filed by Hector Garcia-Santana on behalf of AEP Ohio Transmission Company, Inc. |
02/01/2022
|
Plans & Profile Drawings filed in Compliance with Condition 3 electronically filed by Hector Garcia-Santana on behalf of AEP Ohio Transmission Company, Inc. |
02/01/2022
|
Notice of Supplemental Information for Proof of Compliance with Condition 3 (Plans & Profile Drawings filed separately) electronically filed by Hector Garcia-Santana on behalf of AEP Ohio Transmission Company, Inc. |
01/19/2022
|
Proof of Compliance with Condition electronically filed by Hector Garcia-Santana on behalf of AEP Ohio Transmission Company, Inc. |
01/03/2022
|
Notice of Proof of Compliance with Condition 7 electronically filed by Hector Garcia-Santana on behalf of AEP Ohio Transmission Company, Inc. |
01/03/2022
|
Notice of Proof of Compliance with Condition 12 electronically filed by Hector Garcia-Santana on behalf of AEP Ohio Transmission Company, Inc. |
11/16/2021
|
Notice of Start of Construction electronically filed by Hector Garcia-Santana on behalf of AEP Ohio Transmission Company, Inc. |
11/10/2021
|
Notice of Proof of Compliance with Condition Part 5 (pages 201-259) electronically filed by Hector Garcia-Santana on behalf of AEP Ohio Transmission Company, Inc. |
11/10/2021
|
Notice of Proof of Compliance with Condition Part 4 (pages 161-200) electronically filed by Hector Garcia-Santana on behalf of AEP Ohio Transmission Company, Inc. |
11/10/2021
|
Notice of Proof of Compliance with Condition Part 3 (pages 131-160) electronically filed by Hector Garcia-Santana on behalf of AEP Ohio Transmission Company, Inc. |
11/10/2021
|
Notice of Proof of Compliance with Condition Part 2 (pages 101-130) electronically filed by Hector Garcia-Santana on behalf of AEP Ohio Transmission Company, Inc. |
11/09/2021
|
Notice of Permit and Compliance with Condition Part 1 (pages 1-100) electronically filed by Hector Garcia-Santana on behalf of AEP Ohio Transmission Company, Inc. |
11/09/2021
|
Notice of Proof of Compliance with Condition 21 electronically filed by Hector Garcia-Santana on behalf of AEP Ohio Transmission Company, Inc. |
10/21/2021
|
Service Notice. |
10/21/2021
|
Order on Certificate granting the application filed by AEP Ohio Transmission Company, Inc. to amend its certificate electronically filed by Ms. Mary E. Fischer on behalf of Ohio Power Siting Board. |
09/20/2021
|
Proof of Compliance with the notice requirements electronically filed by Hector Garcia-Santana on behalf of AEP Ohio Transmission Company, Inc. |
08/30/2021
|
Service Notice. |
08/30/2021
|
Staff Report of Investigation electronically filed by BreAnna J. Freeman on behalf of Staff of OPSB. |
07/26/2021
|
In the Matter of the Application for Amendment #2 to the Vigo-Pine Ridge Switch 138 kV Transmission Line Project electronically filed by Mr. Hector Garcia on behalf of AEP Ohio Transmission Company, Inc. |