10/20/2022
|
Notice of Construction Completion and In-Service Date electronically filed by Errin C. Harris on behalf of AMP Transmission, LLC. |
10/28/2021
|
Building Permit Issued electronically filed by Errin C. Harris on behalf of AMP Transmission, LLC. |
10/13/2021
|
Permit Issued - Curb Cut/Drive/Culvert Permit Issued electronically filed by Errin C. Harris on behalf of AMP Transmission, LLC. |
09/14/2021
|
Notice of Approved Excavation Permit Application electronically filed by Errin C. Harris on behalf of AMP Transmission, LLC. |
08/19/2021
|
Notice of Commencement of Construction electronically filed by Errin C. Harris on behalf of AMP Transmission, LLC. |
08/17/2021
|
Notice of Approved Application for a Zoning Certificate electronically filed by Errin C. Harris on behalf of AMP Transmission, LLC. |
06/03/2021
|
Service Notice. |
06/03/2021
|
Staff Report of Investigation electronically filed by Mr. Matt Butler on behalf of Staff of OPSB. |
06/02/2021
|
Ohio EPA Construction Site Stormwater General Permit Issued for the Bellard Substation electronically filed by Errin C. Harris on behalf of AMP Transmission, LLC. |
03/31/2021
|
Notice of Correspondence from the Federal Aviation Administration - Determination of No Hazard to Air Navigation (2 of 2) electronically filed by Errin C. Harris on behalf of AMP Transmission, LLC. |
03/31/2021
|
Notice of Correspondence from the Federal Aviation Administration - Determination of No Hazard to Air Navigation (1 of 2) electronically filed by Errin C. Harris on behalf of AMP Transmission, LLC. |
03/31/2021
|
Public Comment from Dorothy Cromley. |
03/18/2021
|
Notice Proof of Compliance with O.A.C. 4906-6-07 and 4906-6-08 electronically filed by Errin C Harris on behalf of AMP Transmission, LLC. |
03/11/2021
|
Construction Notice Application for the Bellard Substation (Part 3 of 3) electronically filed by Errin C. Harris on behalf of AMP Transmission, LLC. |
03/11/2021
|
Construction Notice Application for the Bellard Substation (Part 2 of 3) electronically filed by Errin C. Harris on behalf of AMP Transmission, LLC. |
03/11/2021
|
Construction Notice Application for the Bellard Substation (Part 1 of 3) electronically filed by Errin C. Harris on behalf of AMP Transmission, LLC. |
03/04/2021
|
In the Matter of the Pre-Application Notification Letter electronically filed by Errin C Harris on behalf of AMP Transmission, LLC. |