DIS - Case Record for 20-1747-EL-BNR Skip to main content
      
      
CASE NUMBER: 20-1747-EL-BNR
CASE DESCRIPTION: Harper-West Akron 138 kV Transmission Line Switch Replacement Project
DOCUMENT SIGNED ON: 10/19/2024
DATE OF SERVICE: ________________________________________
10/15/2021 Construction Completion Notification Letter electronically filed by Ms. Devan K. Flahive on behalf of American Transmission Systems Incorporated.
03/25/2021 Construction Notice Clarifying Non-Encroachment of Project on Floodplain electronically filed by Ms. Devan K. Flahive on behalf of American Transmission Systems Incorporated.
03/22/2021 Notice of Start Construction Letter electronically filed by Ms. Devan K Flahive on behalf of American Transmission Systems Incorporated.
03/17/2021 Service Notice.
03/17/2021 Staff Report of Investigation electronically filed by Mr. Matt Butler on behalf of Staff of OPSB.
12/23/2020 Application Construction Notice for Certificate of Environmental Compatibility and Public Need for Project electronically filed by Ms. Devan K Flahive on behalf of American Transmission Systems Incorporated.
12/09/2020 In the Matter of the Pre-Application Notification Letter for Project electronically filed by Mr. Robert J Schmidt on behalf of American Transmission Systems Inc.