02/16/2022
|
Notice of Construction Completion electronically filed by Ms. Devan K. Flahive on behalf of American Transmission Systems Incorporated. |
12/31/2020
|
Service Notice. |
12/31/2020
|
Staff Report of Investigation electronically filed by Mr. Jason Cross on behalf of Ohio Power Siting Board Staff. |
10/16/2020
|
Construction Notice Application for Certificate of Environmental Compatibility and Public Need for Project electronically filed by Ms. Devan K Flahive on behalf of American Transmission Systems Incorporated. |
09/25/2020
|
In the Matter of the Pre-Application Notification Letter for the Babb-Evans 138 kV Transmission Line Loop to Aetna Substation Project electronically filed by Mr. Robert J. Schmidt on behalf of American Transmission Systems Inc. |