02/12/2021
|
Proof of Compliance with Condition (2) and associated exhibit for the Licking Co-Op Extension – Bladensburg 138kV Transmission Line Project electronically filed by Tanner Wolffram on behalf of Ohio Power Company. |
02/04/2021
|
Notification of Start of Construction for the Licking Co-Op Extension – Bladensburg 138kV Transmission Line Project electronically filed by Tanner Wolffram on behalf of Ohio Power Company. |
12/14/2020
|
Service Notice. (Staff Report) |
12/11/2020
|
Staff Report of Investigation electronically filed by Mark C Bellamy on behalf of OPSB Staff. |
09/28/2020
|
Proof of Compliance associated exhibits for the Licking Co-Op Extension – Bladensburg 138kV Transmission Line Project electronically filed by Tanner Wolffram on behalf of Ohio Power Company. |
09/18/2020
|
Construction Notice for the Licking Co-Op Extension – Bladensburg 138kV Transmission Line Project electronically filed by Tanner Wolffram on behalf of Ohio Power Company. |
09/15/2020
|
In the Matter of the Pre-Application Notification Letter for the Licking Co-Op Extension – Bladensburg 138kV Transmission Line Project electronically filed by Tanner Wolffram on behalf of Ohio Power Company. |