CASE NUMBER: 20-1353-EL-BNR
CASE DESCRIPTION: Apple Valley 138 kV Switch Project
DOCUMENT SIGNED ON: 6/26/2024
DATE OF SERVICE: ________________________________________
03/22/2021 Notice of In-Service Date for the Apple Valley 138 kV Switch Project electronically filed by Tanner Wolffram on behalf of AEP Ohio Transmission Company, Inc.
12/16/2020 Construction Start Notice electronically filed by Tanner Wolffram on behalf of AEP Ohio Transmission Company, Inc.
12/04/2020 Proof of Compliance with Condition (2) and associated exhibit for Apple Valley 138 kV Switch Project electronically filed by Tanner Wolffram on behalf of AEP Ohio Transmission Company, Inc.
12/04/2020 Proof of Compliance with Condition (2) and associated exhibit for Apple Valley 138 kV Switch Project- PART A electronically filed by Tanner Wolffram on behalf of AEP Ohio Transmission Company, Inc.
11/16/2020 Service Notice.
11/16/2020 Staff Report of Investigation electronically filed by Mr. Matt Butler on behalf of Staff of OPSB.
09/24/2020 Notice of Adjustment for the Apple Valley 138 kV Switch Project electronically filed by Tanner Wolffram on behalf of AEP Ohio Transmission Company, Inc.
09/02/2020 Proof of Compliance associated exhibits for the Apple Valley 138 kV Switch Project electronically filed by Tanner Wolffram on behalf of AEP Ohio Transmission Company, Inc.
08/24/2020 Construction Notice Application for the Apple Valley 138 kV Switch Project electronically filed by Tanner Wolffram on behalf of AEP Ohio Transmission Company, Inc.
08/17/2020 In the matter of the Pre-Application Notification Letter for the Apple Valley 138 kV Switch Project electronically filed by Tanner Wolffram on behalf of AEP Ohio Transmission Company, Inc.