04/12/2021 | Notice of Start of Construction Amendment #2 to the Rouse-Bell Ridge 138 kV Project electronically filed by Tanner Wolffram on behalf of AEP Ohio Transmission Company, Inc. | 2 |
12/22/2020 | Service Notice. | 1 |
12/22/2020 | Entry granting the application filed by AEP Ohio Transmission Company, Inc. to amend its certificate electronically filed by Heather A Chilcote on behalf of The Ohio Power Siting Board. | 10 |
11/25/2020 | Service Notice. (Staff Report) | 2 |
11/25/2020 | Staff Report of Investigation electronically filed by Mr. Matt Butler on behalf of Staff of OPSB. | 6 |
08/18/2020 | Proof of Compliance of associated exhibits for the Rouse Bell Ridge 138 kV Transmission Line Project electronically filed by Tanner Wolffram on behalf of AEP Ohio Transmission Company, Inc. | 76 |
08/07/2020 | Amended Application for the Rouse-Bell Ridge 138 kV Transmission Line Project electronically filed by Tanner Wolffram on behalf of AEP Ohio Transmission Company, Inc. | 105 |