09/14/2020
|
Notice of Proof of Compliance with Condition 2 electronically filed by Tanner Wolffram on behalf of AEP Ohio Transmission Company, Inc. |
07/28/2020
|
Start of Construction Notice for the East Lima-Maddox Creek 345 kV Transmission Line Project on August 3, 2020 electronically filed by Tanner Wolffram on behalf of AEP Ohio Transmission Company, Inc. |
07/15/2020
|
Service Notice |
07/15/2020
|
Staff Report of Investigation electronically filed by Mr. Matt Butler on behalf of Staff of OPSB. |
04/23/2020
|
Notice of Proof of Compliance Letter and associated exhibits for the East Lima-Maddox Creek 345 kV Transmission Line Project electronically filed by Tanner Wolffram on behalf of AEP Ohio Transmission Company, Inc. |
04/22/2020
|
Construction Notice Application for the East Lima-Maddox Creek 345 kV Transmission Line Project electronically filed by Tanner Wolffram on behalf of AEP Ohio Transmission Company, Inc. |
04/06/2020
|
In the Matter of the Pre-Application Notification Letter for the East Lima-Maddox Creek 345kV Transmission Line Project electronically filed by Tanner Wolffram on behalf of AEP Ohio Transmission Company, Inc. |