02/25/2021
|
Construction Completion Notification Letter electronically filed by Ms. Devan K. Flahive on behalf of American Transmission Systems Incorporated. |
03/02/2020
|
Construction Notice stating that the project is scheduled to commence on March 9, 2020 filed by S. Humphrys on behalf of FirstEnergy Service Company. |
01/31/2020
|
Service Notice (staff report) |
01/31/2020
|
Staff Report of Investigation electronically filed by Mr. Matt Butler on behalf of Staff of OPSB. |
01/16/2020
|
Construction Notice CIoverdale-Torrey 138 kV Transmission Line Tap to Legend Mod Substation Project filed by Scott M. Humphrys,Transmission Siting Supervisor
Energy Delivery Transmission and Substation Design on behalf of FirstEnergy Service Company. |
12/23/2019
|
In the Matter of the Pre-Application Notification Letter filed by S. Humphrys on behalf of American Transmission Systems, Incorporated and FirstEnergy Service Company. |